Tender call for US$940mn phase I of Chile’s Américo Vespucio Oriente highway

A tender call for the first, US$940 million stretch of the Américo Vespucio Oriente underground expressway (AVO) in Chile’s capital Santiago Chile's has been issued by the public works ministry (MOP). The prized 40-year concession entails building and operating a 9.3km underground expressway running from El Salto avenue to Príncipe de Gales avenue. The tunnel will stretch over two different levels, each one hosting a one-way, three-lane expressway. Road capacity along the route will increase to 8,000 vehicl
August 1, 2013 Read time: 2 mins
A tender call for the first, US$940 million stretch of the Américo Vespucio Oriente underground expressway (AVO) in Chile’s capital Santiago Chile's has been issued by the public works ministry (MOP).

The prized 40-year concession entails building and operating a 9.3km underground expressway running from El Salto avenue to Príncipe de Gales avenue. The tunnel will stretch over two different levels, each one hosting a one-way, three-lane expressway.

Road capacity along the route will increase to 8,000 vehicles per hour from a current 3,000 vehicles per hour, in a push to mitigate the city increasing traffic jams.

The AVO project was originally conceived of to be the missing link in a beltway that runs around Santiago. As such, it was originally earmarked to span underground north to south for 13km, joining El Salto with the Rotonda Grecia.

However, opposition from inhabitants of the La Reina and Peñalolén districts to the last 4km-stretch of the tunnel pushed the government, which is leaving office in March 2014, to split the project and call a tender only for the first 9.3km stretch.

The responsibility for the AVO's final stretch will pass on to the new elected president. The current government led by Sebastian Piñera will leave office four months after the presidential election takes place in November 2013.

Parties interested in bidding for the first stretch have until November 22 to submit their offers.

Related Content

  • Transylvanian motorway breaks new ground in engineering
    July 11, 2012
    Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."
  • Colombian highway project open to tenders
    April 12, 2013
    A major highway project for Colombia has now been opened to tenders. The project is for the Autopistas de la Prosperidad highway and the first five sections of this link have been opened to tender. Only 10 construction firms are being selected to send final bids, while the contracts will be awarded in November 2013. The five sections of the project are expected to cost a total of US$3.52 billion to construct. Overall, all nine sections of Autopista de la Prosperidad will cost $7.15 billion to build. The fou
  • Tendering for new Chile-Argentina tunnel project
    March 21, 2019
    The tender process is open for the study into the planned Paso Las Lenas tunnel to connect Chile and Argentina. The study is expected to cost US$1.55 million and will be paid for by Chile’s O’Higgins Region. The tunnel will be some 11.5km long and the portal in Chile will be at an altitude of 2,020m while the entrance on the Argentine side will be at 2,364m, allowing it to be used throughout the year. The tunnel has an expected pricetag of some $1.67 billion to build, with the countries sharing the construc
  • Colombia’s La Linea Tunnel completion in sight
    May 7, 2015
    The completion of Colombia’s long-running La Linea Tunnel project is now in sight, finally. Colombia’s president, Juan Manuel Santos, and vice president, German Vargas Lleras, made a joint announcement that the 8.65km long tunnel will be inaugurated in November 2016. The two tunnel drives (from Quindio and Tolima) have now met in the middle and only lining works are left to be completed. Once the tunnel is operational, it will enable trucks to complete the journey between Cajamarca (Tolima) and Calarca (Qui