Skip to main content

TBMs cut routes through Wuxi

Often used in road construction in China, eight Herrenknecht tunnel boring machines (TBMs) have now excavated almost 16km of tunnel in 20 months. The machines mastered challenging tunnelling stretches with small overburdens, crossing beneath the emerging metropolis of Wuxi, eastern China, to excavate the first two metro lines in the 3,000-year-old town on Taihu Lake, near Shanghai. Lines 1 and 2, with a total length of 58.5km, are expected to start operation in 2014. A total of five metro lines are planned.
May 29, 2013 Read time: 2 mins
The tunnels going through the city of Wuxi
Often used in road construction in China, eight 2592 Herrenknecht tunnel boring machines (TBMs) have now excavated almost 16km of tunnel in 20 months.

The machines mastered challenging tunnelling stretches with small overburdens, crossing beneath the emerging metropolis of Wuxi, eastern China, to excavate the first two metro lines in the 3,000-year-old town on Taihu Lake, near Shanghai. Lines 1 and 2, with a total length of 58.5km, are expected to start operation in 2014. A total of five metro lines are planned.

The eight Earth Pressure Balance Shields (Ø 6,370–6,390mm) from Herrenknecht have tunnelled through the underground since July 2011 to construct the lines. S-730 TBMs with a top performance of more than 33m/day and 164m/week completed their mission with the breakthrough, excavating a diameter of 6.39m.
Thus, 2,508m of tunnel for metro line 2 was built in only ten months.
Before that the machines also mastered challenging tasks when constructing the metro tunnels for line 1. The S-663, a compact Earth Pressure Balance Shield with a diameter of 6.37m, drove only a few metres beneath residential and commercial buildings, achieving breakthrough late last year.

For more information on companies in this article

Related Content

  • Improving tunneling method selection
    December 11, 2015
    The tunnelling sector remains one of the most active segments of the construction industry worldwide, fuelling demand for equipment However, there have been issues with the efficiency of the selection process for the most suitable tunnelling method for a project in the past. With this in mind, the Italian hydraulic breaker manufacturer Indeco has been working on a new algorithm that allows a contractor to optimise the tunnelling method selection. The firm said that this system has been developed becau
  • Austria's new tunnel meets safety regulations
    July 13, 2012
    New safety regulations and high traffic volumes require new tunnel construction all across Europe. Mike Woof reports Anew highway tunnel now being built in Austria will boost traffic volumes and safety standards on a key European route. The existing Pfänder Tunnel lies close to Austria's borders with Germany and Switzerland and carries a heavy traffic volume, so a new parallel tunnel is under construction to help spread this load, increasing capacity as well as safety. Stringent tunnel safety standards have
  • Take a breather with Herrenknecht’s ventilation shaft boring machine
    February 10, 2016
    For fast underground construction of slot holes with small diameters within highway tunnels, Herrenknecht is highlighting its Boxhole Boring Machine. The BBM is for slot holes, or boreholes, such as ventilation shafts, either inclined or vertical, with diameters of up to 1.5m and lengths of up to 60m. The machines are designed for stable rock with compressive strengths of 180 Megapascal or more. Herrenknecht, based in Schwanau, southwest Germany, uses pipe jacking technology for its BBM. A drilling un
  • Take a breather with Herrenknecht’s ventilation shaft boring machine
    January 6, 2017
    For fast underground construction of slot holes with small diameters within highway tunnels, Herrenknecht is highlighting its Boxhole Boring Machine. The BBM is for slot holes, or boreholes, such as ventilation shafts, either inclined or vertical, with diameters of up to 1.5m and lengths of up to 60m. The machines are designed for stable rock with compressive strengths of 180 Megapascal or more. Herrenknecht, based in Schwanau, southwest Germany, uses pipe jacking technology for its BBM. A drilling un