Stroitelnoe Upravlenie-820 (SU-820) has won a tender for reconstructing 11km of the M-5 Ural federal highway in Russia. SU-820 estimated the work cost at US$103.98million (RUB 3.30bn), which was 18% less that the starting price. The reconstruction is due to be completed by late October 2014. Five other companies including the Chelyabinsk-based (Ural) Uralmotostroy, the Omsk-based (Siberia) Mostovik, and the Saratov-based (Volga) Volgomost, took part in the tender.
June 1, 2012 Read time: 1 min
Stroitelnoe Upravlenie-820 (SU-820) has won a tender for reconstructing 11km of the M-5 Ural federal highway in Russia.

SU-820 estimated the work cost at US$103.98million (RUB 3.30bn), which was 18% less that the starting price. The reconstruction is due to be completed by late October 2014.

Five other companies including the Chelyabinsk-based (Ural) Uralmotostroy, the Omsk-based (Siberia) Mostovik, and the Saratov-based (Volga) Volgomost, took part in the tender.

Related Content

  • Russian roads benefiting from rebuilding programme
    November 30, 2018
    Russia’s Federal Road Agency (Rosavtodor) set out an ambitious plan of road development projects for 2018 and is achieving its target. Compared with 2017, Rosavtodor increased its programme of road development for 2018 by 19.5%. Meanwhile Rosavtodor has planned to repair 8,400km of roads, with 97 of the planned works being completed ahead of schedule. Work to a further four sections of roads are also likely to be completed ahead of schedule in the Leningrad Region, Sverdlovsk Region (Urals), Novosibirsk Reg
  • Major investment planned for Russia’s Federal Road network
    December 10, 2012
    Russia will spend some of its revenues from its oil industry on improving its road network. Some 350km of Federal Roads were built in Russia in 2011 and 230km of Federal Roads have been constructed in Russia so far during 2012. Spending on Russia’s Federal Roads was US$$12.7 billion during this year. The investment in Russia’s Federal Roads is expected to increase to $14.6 billion in 2013, and to $16.6 billion by 2015. The work is needed as just 30% of Federal Roads currently meet requirements. And in capit
  • Moscow-Kazan highway plans
    June 17, 2020
    The Moscow-Kazan highway plans form part of the nation’s future economic recovery.
  • Three bidders have submitted tenders for a key bridge link in Siberia
    August 20, 2012
    Yenisey River at US$394.7 million. The Krasnoyarsk-based Trasmost offered a bid of $450.6 million for the work while another Krasnoyarsk-based firm Sibiryak submitted a tender of $453.9 million for the bridge. This will be the fourth road bridge spanning the Yenisey River in Krasnoyarsk. All three companies said that the work will take 40 months to complete.