STRABAG wins tricky Polish project

Austrian construction firm STRABAG has won a major road contract from Poland’s General Directorate for National Roads and Highways (GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw.
May 2, 2012 Read time: 2 mins
Austrian construction firm 945 Strabag has won a major road contract from Poland’s General Directorate for National Roads and Highways (1361 GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw. The contract is worth some €254 million and the work is now starting and expected to take some 27 months to complete.

It is worth noting that concrete construction will be used for the S8. The work is being carried out in two stretches and the 19km section of S8 between Walichnowy and Zùoczew is for four lanes and includes construction of a junction with the busy National Road 45 as well as 16 bridges.

Due to difficult geological conditions, the area will require a total of 60,000m of piles and 700,000m³ of geotextiles. The construction work will be carried out by local subsidiaries 2861 Hermann Kirchner Polska, STRABAG Sp and Heilit+Woerner Budowlana.

The firm’s bid of €157.4 million was the lowest out of the eight submitted in the tender. Other bidders included 3414 Shanghai Urban Construction Group and the consortia of: 3305 Polimex-Mostostal, Pol-Aqua and PBG.

The second section between Zùoczew and Sieradz Poùudnie is 19.6km long and features two lanes, again using concrete technology. The section also requires the construction of 18 bridges, the conversion of local and municipal roads, as well as the construction of the Dàbrowa Wielka rest area including the technical infrastructure.

The works are being carried out by a consortium of STRABAG Sp and Heilit+Woerner Budowlana. “The difficult subsoil conditions of this project represent a special challenge: our great experience and our technical know-how in this field afforded us a decisive advantage and allowed us to secure the contract,” said STRABAG SE CEO Dr Hans Peter Haselsteiner.

In all GDDKiA has signed contracts for the construction of four sections (2,3,4 and 5) of the S8 road, which measure a total length of over 78km. The value of the contracts is close to €620.6 million.

Related Content

  • Strabag raises 2011-2012 outlook
    May 9, 2012
    After a solid first quarter 2011, Strabag, Central and Eastern Europe’s largest construction company, has raised its outlook for the financial years 2011 and 2012. According to the new forecast, Strabag expects an output volume of €14 billion in 2011 (previous target €13.5 billion), with earnings before interest and taxes (EBIT) forecast to increase to €320 million, after €295 million had been predicted. For 2012, the company had expected an output volume of €13.7 billion and an EBIT of €300 million, whi
  • Winning formula for formwork
    July 19, 2012
    An unusual application of formwork took place recently in France, while formwork using one particular engineering construction kit was used for the first time in Poland. Guy Woodford reports An 80m long wild game underpass is an innovative feature of the Route Nationale 88 (RN 88) expansion in south-west France. For construction of the arched underpass tunnel, a PERI tunnel formwork carriage using VARIOKIT engineering construction kit was used. Thanks to the equipment’s easy handling, along with pre-assembl
  • Kosovo's award-winning green highway construction
    March 20, 2012
    A new highway is proving an economic lifeline for the tiny country of Kosovo – Mike Woof reports. Road projects in Europe rarely meet such widespread public approval and support as the new Route 7 highway being built in the new Balkan state of Kosovo. The first sections of the new road opened to traffic in November 2011, with locals turning out in large numbers to celebrate the event. The official opening was carried out by the country’s prime minister Hashim Thaçi, president Atifete Jahjaga, and members of
  • Poland's complex road dispute
    March 1, 2012
    The complex legal case between the Polish General Directorate for National Roads and Motorways (GDDKiA) and Austrian contractor Alpine Bau is continuing in the Polish courts.