STRABAG wins tricky Polish project

Austrian construction firm STRABAG has won a major road contract from Poland’s General Directorate for National Roads and Highways (GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw.
May 2, 2012 Read time: 2 mins
Austrian construction firm 945 Strabag has won a major road contract from Poland’s General Directorate for National Roads and Highways (1361 GDDKiA). The deal is for the construction of a 40km section of the S8 Expressway between Walichnowy and Sieradz Poùudnie, some 240km to the south west of capital Warsaw. The contract is worth some €254 million and the work is now starting and expected to take some 27 months to complete.

It is worth noting that concrete construction will be used for the S8. The work is being carried out in two stretches and the 19km section of S8 between Walichnowy and Zùoczew is for four lanes and includes construction of a junction with the busy National Road 45 as well as 16 bridges.

Due to difficult geological conditions, the area will require a total of 60,000m of piles and 700,000m³ of geotextiles. The construction work will be carried out by local subsidiaries 2861 Hermann Kirchner Polska, STRABAG Sp and Heilit+Woerner Budowlana.

The firm’s bid of €157.4 million was the lowest out of the eight submitted in the tender. Other bidders included 3414 Shanghai Urban Construction Group and the consortia of: 3305 Polimex-Mostostal, Pol-Aqua and PBG.

The second section between Zùoczew and Sieradz Poùudnie is 19.6km long and features two lanes, again using concrete technology. The section also requires the construction of 18 bridges, the conversion of local and municipal roads, as well as the construction of the Dàbrowa Wielka rest area including the technical infrastructure.

The works are being carried out by a consortium of STRABAG Sp and Heilit+Woerner Budowlana. “The difficult subsoil conditions of this project represent a special challenge: our great experience and our technical know-how in this field afforded us a decisive advantage and allowed us to secure the contract,” said STRABAG SE CEO Dr Hans Peter Haselsteiner.

In all GDDKiA has signed contracts for the construction of four sections (2,3,4 and 5) of the S8 road, which measure a total length of over 78km. The value of the contracts is close to €620.6 million.

Related Content

  • Tanzania road development projects being planned
    March 24, 2017
    A series of major road projects are now being planned in Tanzania, with funding sources for much of the work having been identified and secured. The largest of these is being delivered with a World Bank loan worth US$425 million, which will help pay for transport improvements in Tanzania’s capital, Dar es Salaam.
  • Balfour Beatty begins construction of €23.05mn Merseyside motorway link
    January 31, 2014
    Balfour Beatty this week began construction on a €23.05 million (£19 million) scheme to bypass two congested villages and link communities in Sefton along the west coast of Merseyside in Northwest England directly to the M57 and M58 motorways. The road will be 4.5km long and connect the A565 Southport Road to the motorway junction at Switch Island, avoiding the villages of Thornton and Netherton. The newly designated A5758 Broom’s Cross Road will relieve long-standing traffic issues in the area and provid
  • China looks to the future with major highway plans
    February 15, 2012
    China is still moving ahead with plans that will give it the world's biggest highway system. Patrick Smith reports. As China's economy grows even more, keeping the country on the move has become a priority for the government. While the country has made great strides over the past decade in improving its infrastructure, the number of vehicles has also increased rapidly, and in some instances restrictions have been placed on them.
  • Bridge formwork solutions complete big bridge picture
    July 2, 2014
    Advanced bridge formwork solutions are allowing contractors to complete vital major highway infrastructure projects covering Norway, Sweden, Estonia and Poland. Guy Woodford reports Building the Labbdalen bridges in Norway is a key feature of the E6 highway improvement programme. Main project contractor HÆHRE tasked RMD Kwikform and Teknikk with supplying a complete formwork and shoring solution that could tackle the challenging Norwegian terrain, whilst preserving the environment. Situated two hours