Slovakia’s troubled D1 highway

Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.
February 20, 2012 Read time: 2 mins
2875 Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.

The move towards state funding is a major change in policy as the highway was originally planned to be paid for through a PPP by the Slovenske Dialnice consortium, which had won the concession for the project.

However, the deal was cancelled and Slovenske Dialnice has said it will dispute a €10 million fine being imposed by the Ministry for allegedly not being able to secure finance for the construction and operation of the Martin-Presov section.

Slovak construction firm 2877 Doprastav, which was part of the Slovenske Dialnice consortium, said that it secured finance worth €1.66 billion from 18 commercial banks. Of this, €1 billion was from the 1054 European Investment Bank (EIB); €190 million from the 1166 European Bank for Reconstruction and Development (EBRD) and €379 million from other sources. The total finances available for the project totalled €3.23 billion, which was sufficient for the project, according to Doprastav.

The construction companies claim the project failed due to objections stemming from environmental groups, for which the government is responsible, and the EIB and EBRD expressed concern over the D1 project when the environmental issues were revealed.

Questions were raised regarding the legality of the environmental impact assessment, which resulted in the project being scrutinised by the 2465 European Commission. After this the EIB and EBRD showed reservations as pushing ahead with the project as it stood could end in a legal tangle at the European Court of Justice.

Following elections in Slovakia a new administration took power and announced its concern over the cost of the D1 project, although the consortium did manage to reduce the budget required for the work by addressing bank interest charges. Responsibility for the original environmental impact assessment may prove to be the key to this complex legal tangle.

Related Content

  • Poland's highway plans to go ahead
    May 15, 2012
    In Poland, the European Investment Bank has committed itself to maintaining its loan agreement for the A1 highway, despite recent problems over the project. The e1.1 billion loan that the EIB had agreed with Autostrada Poludnie for construction of a 180km section of the A1 highway from Strykow to Pyrzowice, will now be placed at the disposal of the Polish highway authorities. To carry out the work, Poland has to raise a further e503 million, which could be obtained from an issue of road bonds. Autostrada Po
  • Delays to highway, tunnel and bridge building
    May 14, 2012
    The Slovakian government is being asked for financial compensation by Granvia, the group building the country’s new Nitra-Banska Bystrica highway. Granvia is building the highway under the PPP model through a 30-year concession deal. The compensation has been requested due to delays that have been caused by the need for archaeological investigations along the route.
  • New Slovakia highway opening for traffic
    November 26, 2015
    Stretches of a major new highway project in Slovakia are opening for traffic. Two sections of the D1 highway are opening by the end of 2015. Slovakian National Motorway Company has said that the second section of the 9.5km D1 highway stretch from Janovce-Jablonov, near the town of Levoca, will open by the end of 2015. The other section set to open will be the D1 stretch from Fricovce – Svinia and located near Presov. During 2015 NDS planned to open five new motorway stretches, of which three are already in
  • Reducing highway construction costs
    May 15, 2012
    Cost reductions sought The transport authorities in Montenegro are still considering ways to reduce the construction costs of the Bar-Boljare highway. Croatian company Konstruktor is still keen to work on the highway project, which it priced at €2.7 billion. The Montenegro government cancelled Konstruktor’s concession agreement for the project recently. The Israeli-Greek consortium comprising Aktor, Shikun and Binui-HCH was the second ranked bidder for the project and is in talks with the Montenegro gove