Slovakia’s troubled D1 highway

Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.
February 20, 2012 Read time: 2 mins
2875 Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.

The move towards state funding is a major change in policy as the highway was originally planned to be paid for through a PPP by the Slovenske Dialnice consortium, which had won the concession for the project.

However, the deal was cancelled and Slovenske Dialnice has said it will dispute a €10 million fine being imposed by the Ministry for allegedly not being able to secure finance for the construction and operation of the Martin-Presov section.

Slovak construction firm 2877 Doprastav, which was part of the Slovenske Dialnice consortium, said that it secured finance worth €1.66 billion from 18 commercial banks. Of this, €1 billion was from the 1054 European Investment Bank (EIB); €190 million from the 1166 European Bank for Reconstruction and Development (EBRD) and €379 million from other sources. The total finances available for the project totalled €3.23 billion, which was sufficient for the project, according to Doprastav.

The construction companies claim the project failed due to objections stemming from environmental groups, for which the government is responsible, and the EIB and EBRD expressed concern over the D1 project when the environmental issues were revealed.

Questions were raised regarding the legality of the environmental impact assessment, which resulted in the project being scrutinised by the 2465 European Commission. After this the EIB and EBRD showed reservations as pushing ahead with the project as it stood could end in a legal tangle at the European Court of Justice.

Following elections in Slovakia a new administration took power and announced its concern over the cost of the D1 project, although the consortium did manage to reduce the budget required for the work by addressing bank interest charges. Responsibility for the original environmental impact assessment may prove to be the key to this complex legal tangle.

Related Content

  • Sarajevo Ring Road works set to finish in October 2012
    July 27, 2012
    The Sarajevo Ring Road in Bosnia and Herzegovina is expected to be completed by October 2012. The construction of the 5.6km long highway from Josanica to Butila is being carried out by a consortium of companies made up of HP Investing and Strabag AG. The completed Ring Road will be part of the future Corridor Vc motorway.
  • Changing policy for Europe’s road funding?
    August 27, 2013
    The 2011 EC White Paper on Transport acknowledges that transport is the backbone of Europe’s economy, directly employing 10 million people and accounting for approximately 5% of EU GDP. In addition, it recognises that ‘infrastructure shapes mobility’ and that ‘curbing mobility is not an option’. Given the importance policymakers place on the ability to move people and goods seamlessly across Europe, it becomes rather hard to explain why they have neglected for so long the main ‘vehicle’ for mobility acro
  • Despite earlier contractor issues, road projects in Bosnia are proceeding on track
    May 16, 2012
    Key road construction projects are now moving forward in Bosnia with work on-track for the Sarajevo ringroad as well as the Corridor Vc highway. Construction of a 130km section of the Corridor Vc highway should be complete by 2014 according to Bosnia's Ministry of Transport and Telecoms. Work on the first section of the Sarajevo ringroad should be completed within five months, following the signing of an agreement worth €17 million between the Austrian firm Strabag and the Bosnian company HP Investing. The
  • Chilean highway project faces questions
    February 14, 2012
    The plans for Chile's new Vespucio Oriente highway are under a question mark at present. The Chilean Construction Chamber (CChC) and the association of concession-holders (COPSA) have raised concerns over the plans by the country's government to press ahead with the construction of the 13km Vespucio Oriente highway in capital Santiago.