Slovakia's D1 highway moving ahead

Slovakia's Transport Ministry has been working with highway firm NDS on a highway construction programme for the 2011-2014 period.
March 1, 2012 Read time: 1 min
Slovakia's Transport Ministry has been working with highway firm NDS on a highway construction programme for the 2011-2014 period. The programme calls for five tenders for five sections of the D1 highway. These five sections were part of the PPP project for the D1 highway, which was cancelled due to funding issues. Construction work on the Dubna Skala-Turany, Turany-Hubova, Hubova-Ivachnova, Janovce-Jablonov and Fricovce-Svinia stages of the D1 will start from the middle of this year through to the second quarter of 2012. In all these sections will total 75km and are due for completion in 2013-2015.

The tender for the 11.2km stage of the D1 from Fricovce-Svinia is open and is expected to cost €213.2 million, while the work will take three years to complete. Funding will be provided by the 3287 EU Cohesion Fund and the government budget funds within the Operational Programme Transport. Slovakia's Transport Ministry hopes to open the Turany-Hubova section of the D1 highway by 2015. The Transport Ministry has said that Slovakia will meet criteria for EU funding for the project in spring 2011.

For more information on companies in this article

Related Content

  • Delays ahead for Slovakia’s Visnove tunnel
    September 5, 2018
    Slovakia's transport ministry says the 7.5km Visnove tunnel near Zilina, part of the D1 motorway, will be delayed by two years to open in 2022. The recent announcement came as the ministry agreed to an extension to the construction permit held by Salini Impregilo for work on the twin-tube tunnel. The design-and-build contract worth about €410 million was assigned to the Salini Impregilo-led joint venture DUHA in 2014 by the National Highway Company NDS.
  • Slovakia tunnel excavation complete
    September 21, 2018
    Excavation work on Slovakia’s Visnove Tunnel has now been completed. Driving the tunnel took nine months longer than originally anticipated. The 7.5km tunnel will be Europe’s seventh longest when complete and forms part of the D1 highway between Dubna Skala and Lietavska. Work on this highway started in 2014, with the construction being carried out jointly by Italian contractor Salini Impregilo and local firm Duha. Fitting out of the tunnel is now commencing, with equipment such as ventilation and traffic
  • Višňové Tunnel delays continue
    June 21, 2022
    What will be Slovakia’s longest tunnel at 7.5km is facing more technical issues, according to the contractor Skanska.
  • Slovakia opens up more D1 motorway sections to tender
    June 9, 2015
    Slovakia’s national motorway company NDS has put out to tender two sections of the D1 motorway near Presov and Kosice. Both tenders have been published in the Official Journal of the European Union, with bid submission deadlines set for June 29. The first section is the south-west D1 by-pass of Presov at nearly 8km long, including the construction of a 2km duel-tube road tunnel Presov and estimated to cost €443.4 million. The second section is the 14.5km-long D1 Budimir to Bidovce stretch, with cost