Sarens completes Nantes area A11 bridge lift

In France, Sarens used four Kamag SPMTs – self-propelled modular transporters – to move a bridge deck 70m and place it over the A11 at the autoroute’s Portes de Gesvres interchange.
By David Arminas December 27, 2023 Read time: 3 mins
Because the job site was located along the A11 autoroute, there was limited space and access for vehicles and equipment (image courtesy Sarens)

Heavy lift specialist Sarens reports that it successfully maneuvered a 740-tonne bridge deck into place as part of A11 autoroute upgrade work near Nantes, France.

The 343km-long A 11 autoroute – also called L'Océane - connects Paris with Nantes via Le Mans and Angers. Sarens Technical Solutions and Engineering conducted the lift on behalf of customer Bouygues Travaux Publics Régions France and owner VINCI Autoroutes. The Sarens team successfully jacked up, transported and installed the 110m-long curved steel structure at the A11’s Portes de Gesvres interchange.

Equipment involved four Kamag SPMTs – self-propelled modular transporters - with six axle lines each. There were four CS450 towers with 12 elements on one side and another four CS450 towers with 10 elements on the other side.

The CS450, in particular, was chosen for its higher elements that allow the crew to jack down faster. This was especially important due to the project’s exacting time constraints. The A11 would be closed for only six hours during the night, giving the crew limited time to drive the SPMTs the 70m from where the bridge deck was constructed and successfully jack down the structure into place, over the four lanes of the A11.

Sarens notes that apart from the actual lift, there were other on-site challenges. First, because the job site was located along the highway, it meant there would be limited space and access for vehicles and equipment. For example, only one truck was allowed to enter the work site at a time. This meant that the crew had to meticulously follow a precise transport schedule.

Meanwhile, the road itself was a challenge. The crew would have to drive 70m across the A11 that was angled in two directions, with up to 4.5% in one direction requiring maximum SPMT stroke.

The necessary equipment arrived via 13 trucks from various locations around Europe. The crew assembled the SPMTs and their transport structure within one day, thanks to a well-coordinated pre-assembly effort at Sarens headquarters in Wolvertem, near Brussels in Belgium.

Next, it was time to jack-and-pack the 740-tonne curved bridge, jacking it from 1.5m to 4m high. From there, the CS450s took over. Positioned on top of the SPMTs, they lifted the bridge at an angle of 5% along its width for transporting it over 70m of highway. Finally, the crew jacked it down 2m onto its final supports – all within the brief six-hour timeframe.

Sarens noted that its team - especially the project team, engineers and eight on-site crew members - worked with usual precision and professional skill to make the installation a success.

For more information on companies in this article

Related Content

  • The Mersey Gateway bridge project continues on schedule
    October 18, 2016
    Work continues on the 2.3km Mersey Gateway signature bridge project close to Liverpool in the UK. David Arminas reports on some of the construction highlights. Under construction is a cable-stayed structure with three towers that will span the Mersey River’s expansive mud flats between the towns of Runcorn and Widnes near Liverpool. Including the approach viaducts on each side, it will be 2.3km long with a river span of 1km. The main bridge deck will be reinforced concrete. The 80m-high central tower will b
  • Cebu-Cordova Link Expressway opens
    April 28, 2022
    The 8.5km expressway, in which Cowi was owners engineer for the client Metro Pacific Tollways, incorporates the longest and tallest bridge in the Philippines.
  • Landmark bridge for Italy?
    August 9, 2023
    The news that the Italian Government is once again considering building a bridge spanning the Messina Strait is of major significance for the construction sector, as well as for the country.
  • France to complete cycling network by 2030
    March 28, 2023
    Around 510km were created last year to the national network in an effort to get even hesitant cyclist onto their bicycles as a means of getting to work and also getting out to play, in the city or the countryside.