Sarajevo Ring Road works set to finish in October 2012

The Sarajevo Ring Road in Bosnia and Herzegovina is expected to be completed by October 2012. The construction of the 5.6km long highway from Josanica to Butila is being carried out by a consortium of companies made up of HP Investing and Strabag AG. The completed Ring Road will be part of the future Corridor Vc motorway.
July 27, 2012 Read time: 1 min
RSSThe Sarajevo Ring Road in Bosnia and Herzegovina is expected to be completed by October 2012.

The construction of the 5.6km long highway from Josanica to Butila is being carried out by a consortium of companies made up of 5576 HP Investing and 945 Strabag AG. The completed Ring Road will be part of the future Corridor Vc motorway.

Bosnia and Herzegovina Federal Minister of Transport and Telecoms, Enver Bijedic, and State Minister of Telecoms and Transport and Director of the roads company JP Ceste FBiH, Filip Vujevo, recently visited the Sarajevo Ring Road construction site. The project has received US$20.54million from the European Bank for Reconstruction & Development (EBRD) and the 1054 European Investment Bank (EIB).

For more information on companies in this article

Related Content

  • Work commencing on key New Zealand tunnel link
    August 3, 2012
    New Zealand prime minister John Key led an official ground-breaking ceremony this week to allow the start of excavation work for two new 2.4km-long motorway tunnels beneath suburban Auckland. The Waterview Connection project is on schedule to begin its main construction phase next year, and the prime minister was on hand to turn the first soil for a 30m-deep trench which is needed to allow access for the tunnels’ southern approach trench in the west Auckland suburb of Owairaka.
  • Strabag wins €83.3mn Bosnia motorway contract
    September 17, 2013
    Strabag has won an €83.3 million contract to build a 10.4km section of the Corridor 5c motorway in Bosnia. The major contract for the Svilaj-Odžak section of the international motorway corridor includes the construction of highway, the border crossing at Svilaj, the Svilaj toll station, two service areas and two motorway exits.
  • Bosnian road toll charges to increase by over 100%
    June 22, 2012
    Road tolls in Bosnia are to rise by over 100%. Director of the Bosnian motorways company Autoceste FBiH, Ensad Karic, said the federal government Federal Bosnia and Herzegovina had approved the increase, effective from 13 June, 2013. Prices for personal vehicles will increase from BAM 2 to BAM 4.20 (US$2.68) on the Sarajevo-Zenica 37km motorway.
  • Slovakia’s troubled D1 highway
    February 20, 2012
    Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.