Sanibel Causeway restoration completed

US$328m project restores Florida causeway devastated by Hurricane Ian in 2022
By Liam McLoughlin June 2, 2025 Read time: 2 mins
The restored three-mile causeway that has re-established the link between Sanibel Island and mainland Florida that was devastated by Hurricane Ian in 2022. Image: Superior Construction

The joint venture team of Superior Construction and de Moya says it has substantially completed the US$328m restoration project Sanibel Causeway in Florida.

The project has re-established and fortified the critical three-mile lifeline between Sanibel Island and mainland Florida that was devastated by Hurricane Ian on September 28, 2022.

When Hurricane Ian destroyed the causeway, Sanibel and Captiva Islands were completely cut off, paralyzing the tourism-dependent economy and leaving residents stranded.

The emergency response team restored temporary access in 15 days, enabling first responders to reach the islands and allowing residents to begin recovery efforts.

“What makes this project special is that we’ve given this community infrastructure they can rely on through whatever comes next,” said Toby Mazzoni, project manager at Superior Construction. “We build for the long haul, especially when communities are counting on us most.”

The project marked the Florida Department of Transportation’s first phased design-build contract and highlighted the JV team’s innovative approach, enabling emergency and permanent repairs to start while the design was still in development. The JV team successfully navigated complex logistics while maintaining traffic flow throughout construction.

“The joint-venture team overcame this project’s logistical challenges with tenacity,” said Superior Construction CEO Nick Largura. “Building five seawalls during the hurricane season, railing in high-quality armor stone materials from Alabama and Georgia quarries, and improving resilience, while collaborating with multiple stakeholders on a first-of-its-kind phased design-build contract, is a monumental feat. I’m incredibly proud of this team.”

At peak construction, the JV team coordinated multiple specialized crews simultaneously: three for pile-driving, four for earthwork, two for storm drainage, six for rebar tying, eight for concrete placement and three for asphalt paving, all while keeping two lanes of traffic open for island residents and visitors.

The rebuilt causeway now features dramatically enhanced storm resilience, including steel sheet pile wall systems, concrete caps, strategically placed armor stone, elevated seawalls, advanced stormwater drainage systems throughout the causeway, 19,500 tonnes of asphalt pavement, and various permanent roadway concrete barriers.
  
The project’s resilience was put to the test during construction when 2024’s Hurricanes Debby, Helene and Milton struck Florida. Completed sections withstood these storms intact, while unfinished areas experienced washouts, providing real-world validation of the JV team’s engineering approach.

The joint venture partners say the causeway’s completion marks a significant milestone in Sanibel Island’s recovery from Hurricane Ian and strengthens the community’s defense against future storms. With this critical infrastructure restored, emergency services can now reliably reach the island, residents have secure mainland access, and tourism-dependent businesses can fully resume operations, revitalizing the island community.

Related Content

  • Transylvanian motorway breaks new ground in engineering
    July 11, 2012
    Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."
  • Poor pedestrian safety record
    March 25, 2021
    The US has a poor pedestrian safety record.
  • Vögele MT 3000-2 for Austria A2 motorway
    May 14, 2014
    Road construction work with moving traffic always represents a major challenge. This is especially true when only one lane can be closed, consequently leaving little space for working and manoeuvring. That was exactly the case for a rehabilitation project on the A2 motorway in Austria between Vienna and Graz near Schäffern. However, the job was further complicated by another factor: all access roads to the job site were roughly 1km apart. Ensuring an uninterrupted supply of mix to the paver under these
  • LA1 bridge project faces construction delay
    February 9, 2023
    The Department of Transportation and Development in the US state of Louisiana said delay to the US$57.7 million project could be as much as 10 months.