San Ignacio de Moxos-Trinidad road scheme in Bolivia to go ahead

Bolivian president Evo Morales said the 77.8km San Ignacio de Moxos-Trinidad road scheme would still go ahead – despite the temporary suspension of work on a contentious section of the route. President Morales’ assurance over the completion of the road, the final section of the highway link between Cochabamba-Beni, was given amid strong objections to the San Ignacio de Moxos-Villa Tunari stretch passing through the TIPNIS natural park.
November 23, 2012 Read time: 2 mins
Bolivian president Evo Morales said the 77.8km San Ignacio de Moxos-Trinidad road scheme would still go ahead – despite the temporary suspension of work on a contentious section of the route.

President Morales’ assurance over the completion of the road, the final section of the highway link between Cochabamba-Beni, was given amid strong objections to the San Ignacio de Moxos-Villa Tunari stretch passing through the TIPNIS natural park.

The San Ignacio de Moxos-Trinidad road scheme is currently in the State Contract System (Sicoe) and, under the terms of an international tender, a total of US$77.90 million has been guaranteed by the government to build the road, which must be completed within 54 months.

A total of 19 indigenous leaders along the road scheme’s route have approved the project, so a public consultation is not needed. To date, a total of 53 communities have approved a road via TIPNIS, with only three opposing. Nazaret Flores, a local leader, said he did not believe that indigenous communities had rejected the road scheme, but were against the part of the project that passes through the TIPNIS natural park.

Related Content

  • Transylvanian motorway breaks new ground in engineering
    July 11, 2012
    Normally in hilly ground, we would use the excavated soil from the cuttings to fill the valleys," says Bogdan Sgarcitu, External Affairs Manager of construction company Bechtel. "But on this stretch the clay-like soil cannot be compacted, so we've had to use many more piles than normal: in just three months we installed more than 500, some drilled as deep as 24m. We've also had to transport millions of tonnes of materials over some less-than-perfect infrastructure."
  • Brussels road tunnel project complete
    March 1, 2022
    Construction work is complete on a key Brussels road tunnel project.
  • Bolivia highway upgrade project planned
    March 3, 2016
    Work on a new dual lane highway connecting La Paz with Santa Cruz in Bolivia is set to cost US$1 billion. The work will be complete by 2019 and the route will link La Paz with Santa Cruz, running through Cochabamba. The Bolivian Ministry of Public Works says that this project will be carried out in addition to previous developments to the road system between La Paz and Oruro. The project to connect different regions includes the 28km double lane highway for El Sillar, as well as tunnels and viaducts. This
  • Rebuild project for historic Pennsylvania bridge
    September 10, 2015
    Rebuilding work is planned for a historic bridge in the US state of Pennsylvania to ensure it remains able to carry current traffic volumes. The work is being managed by consulting engineer Michael Baker International. Pennsylvania Department of Transportation (PennDOT) selected Michael Baker International for the US$5 million engineering and design project that will focus on the western spans of the Market Street Bridge in Harrisburg. Rehabilitating this critical traffic artery in Pennsylvania's capital re