Romania set to start Sebes-Turda motorwa construction

Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges. Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania. Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the European Union as grants and the central gover
November 7, 2014 Read time: 2 mins
Construction of the proposed Sebes-Turda motorway will start by the end of November, according to Eugen Cecan, director of Romania’s Regional Administration for Roads and Bridges.

Cecan made the announcement in Cluj, the second most populous city in Romania after the capital Bucharest and considered the unofficial capital to the historic province of Transylvania.

Cost of the 70km project is around US$500.34 million (€400 million), with 85% coming from the 1116 European Union as grants and the central government investing the remaining 15%.

Cecan said the motorway will be completed by March 2016 and run north from Sebes, with a population of around 25,000, to Turda with a population of 45,000.

Sebes is at the crossroads of two main highways in Romania: E68 European route - DN1 coming from Sibiu and going towards Deva and E81 European route - DN7 coming from Sibiu and going towards Alba-Iulia and Cluj.

Construction work on the motorway is split into four contracts, awarded last year.

Lot 1 – 17km from the highway entrance near the interchange with the A1 motorway at Sebeș to Paraul Iovului – was awarded to the Italian consortium 7809 Salini Impregilo at a cost of nearly $151 million (539,488,704 lei).

Lot 2, around 24km from Paraul Iovului to Aiud, was awarded to an Italian-Romanian consortium that includes RCM Costruzioni, Shelter Construct and Eurocerad International for nearly $128.5 million (460,019,270 lei).

The 12.5km Lot 3 section from Aiud to the Decea interchange is being built by the consortium of Tirrena Scavi and Societa Italiana per Condotte d'Acqua at a cost of cost of $117.5 million (420,511,921 lei).

Lot 4, around 16km from the Decea interchange to the interchange with the A3 motorway near Turda, was awarded to the Romanian division of 3976 Porr Group, Porr Construct SRL, German division Porr Bau, for a cost of $131.4 million (470,004,894 lei).

For more information on companies in this article

Related Content

  • Romania develops road plan
    March 31, 2021
    Romania has developed a road improvement plan.
  • Contractor bankruptcy delays Romanian road project
    July 26, 2013
    The recent bankruptcy of the Austrian contractor Alpine Bau has affected a number of key projects across Europe in countries including Norway, Poland and now Romania. Following Alpine Bau’s bankruptcy, Romania’s national roads authority, CNADNR, cancelled the Austrian contractor’s contract to build a section of highway from Nadlac-Arad. So far, Alpine Bau has been paid €69.5 million to build a 16.6km section of the highway and around 85% of the work has been completed. It is not clear at this stage how the
  • Višňové Tunnel delays continue
    June 21, 2022
    What will be Slovakia’s longest tunnel at 7.5km is facing more technical issues, according to the contractor Skanska.
  • Work to start on section of Bulgaria’s controversial Struma road
    August 19, 2016
    Work will start next month on a 24km section of Bulgaria’s controversial Struma Highway, part of the the Pan-European Corridor IV. Corridor IV runs from Dresden in Germany to Istanbul in western Turkey. The route, named after the Struma River, is part of Е79 that runs from Miskolc in Hungary to the Greek Aegean port of Thessaloniki, passing through the Romanian cities of Deva and Craiova. The 156km route has been under construction in four sections, with work on the third and final section now abou