Renfrew Bridge opening tests complete

The 184m-long cable-stay bridge near Glasgow, Scotland, will be the first road bridge across the River Clyde to open for passing ships.
By David Arminas August 28, 2024 Read time: 2 mins
The cable stay system is similar to Scotland’s Queensferry Crossing bridge - a twin-leaf design with each leaf opening and closing horizontally (image courtesy Graham Construction)

The first operational working of the Renfrew Bridge near Glasgow, Scotland has been accomplished ahead of the bridge opening by the end of this year.

Main contractor Graham said it will continue commissioning works for the bridge that will be the first road bridge across the River Clyde to open for passing ships. The 184m-long cable-stay two-lane road bridge will carry vehicles, pedestrians and cyclists between Glasgow and West Dunbartonshire.

The cable stay system is similar to the Queensferry Crossing - a twin-leaf design with each leaf opening and closing horizontally. Most commercial ships travel on the river during high tide, which happens once during the day and once during the night. When this happens, the bridge will be closed to road traffic, with signs nearby and information online providing advance notice of any closure to all people to plan ahead.

There will be new walking and cycling routes alongside all new roads through Renfrew and across the bridge.

The bridge is central to the major Clyde Waterfront and Renfrew Riverside redevelopment. “It was great to see the bridge closing for the first time in such a smooth, controlled and seamless operation,” said Jim Armour, project director at Graham, a privately-owned national construction company with a €1.32 billion turnover.

The two sections of the bridge were manufactured in the Netherlands and barged over, passing up the English Channel and then up the Irish sea to the site earlier this year.

The project is jointly funded by the UK and Scottish governments through the €1.32 billion Glasgow City Region, a partnership of eight councils working together.

For more information on companies in this article

Related Content

  • Scottish trial for OTT HydroMet’s ecoLog 1000
    April 25, 2022
    An OTT ecoLog 1000 water level logger with cellular data connection to Hydromet Cloud was trialled upon the Vales Burn Bridge in Scotland.
  • UK smart motorway work for M4 link
    September 16, 2019
    Highways England in the UK is carrying out major upgrade work for the busy M4 motorway, running west from capital London. In all 11 bridges are being replaced along a 51km stretch of the M4 between London and Reading. When complete, the current hard shoulder will have been rebuilt and resurfaced to allow traffic to use it as a live lane. The section carrying the heaviest traffic, between the M25 ring road around London and the main exit for Heathrow Airport, will be widened so that it will feature five la
  • $270 million Tanzania bridge opens
    July 2, 2025
    A $270 million bridge has opened in Tanzania.
  • RiverLinx consortium inks London’s Silvertown Tunnel deal
    November 27, 2019
    The RiverLinx consortium has reached financial close on the €1.17 billion Silvertown Tunnel project after a three-year procurement process by the client Transport for London.