Renfrew Bridge opening tests complete

The 184m-long cable-stay bridge near Glasgow, Scotland, will be the first road bridge across the River Clyde to open for passing ships.
By David Arminas August 28, 2024 Read time: 2 mins
The cable stay system is similar to Scotland’s Queensferry Crossing bridge - a twin-leaf design with each leaf opening and closing horizontally (image courtesy Graham Construction)

The first operational working of the Renfrew Bridge near Glasgow, Scotland has been accomplished ahead of the bridge opening by the end of this year.

Main contractor Graham said it will continue commissioning works for the bridge that will be the first road bridge across the River Clyde to open for passing ships. The 184m-long cable-stay two-lane road bridge will carry vehicles, pedestrians and cyclists between Glasgow and West Dunbartonshire.

The cable stay system is similar to the Queensferry Crossing - a twin-leaf design with each leaf opening and closing horizontally. Most commercial ships travel on the river during high tide, which happens once during the day and once during the night. When this happens, the bridge will be closed to road traffic, with signs nearby and information online providing advance notice of any closure to all people to plan ahead.

There will be new walking and cycling routes alongside all new roads through Renfrew and across the bridge.

The bridge is central to the major Clyde Waterfront and Renfrew Riverside redevelopment. “It was great to see the bridge closing for the first time in such a smooth, controlled and seamless operation,” said Jim Armour, project director at Graham, a privately-owned national construction company with a €1.32 billion turnover.

The two sections of the bridge were manufactured in the Netherlands and barged over, passing up the English Channel and then up the Irish sea to the site earlier this year.

The project is jointly funded by the UK and Scottish governments through the €1.32 billion Glasgow City Region, a partnership of eight councils working together.

For more information on companies in this article

Related Content

  • New truck parking facilities for major UK route
    May 26, 2016
    Contractor Balfour Beatty is to construct new truck parking facilities alongside the M20 motorway in Kent in the UK. The package of works was awarded by Highways England and the £130 million deal covers the development of the proposals during the Early Contractor Involvement (ECI) phase of the project. This deal also includes the construction of the lorry area subject to a decision to proceed from the UK Government. The £250 million truck parking area was initially announced by the UK’s Chancellor of the Ex
  • Italy's new southern highway route
    May 13, 2021
    An important new highway route is currently under construction in South Italy
  • Testing and striping underway for Seattle’s Alaskan Way tunnel
    October 18, 2018
    Crews have been working flat out on the Alaskan Way Tunnel in Seattle to install and test thousands of components and 90 interconnected systems.The client, Washington State Department of Transportation, said that Seattle Tunnel Partners began installation inside the double-deck State Route 99 tunnel in March after crews completed construction of the upper and lower roadways. STP said that testing could be complete by late September and the tunnel could open as soon as this fall after an approximate three-w
  • On track with Doka – Çanakkale 1915 Bridge takes shape
    October 1, 2021
    Since delivering an engineering solution for the monumental Çanakkale 1915 Bridge, Doka Turkey has continued its work on this record-breaking project as it takes another step towards its scheduled completion, in time for the country’s centennial in 2023