Progress is being made with Serbia’s Corridor 11 highway project

Work is underway in Serbia for the Corridor 11 highway project and a number of local firms are now carrying out construction work on the Corridor 11 section from Ub to Lajkovac. Meanwhile Azvirt from Azerbaijan is preparing the Ljig to Preljina stretch of the highway, with the €300 million work being financed by Azerbaijan. The Serbian Government is asking China’s Exim Bank for a long term loan of €850 million, of which €300 million would be for the Corridor 11 project and €550 million would be for the Mora
October 8, 2012 Read time: 2 mins
Work is underway in Serbia for the Corridor 11 highway project and a number of local firms are now carrying out construction work on the Corridor 11 section from Ub to Lajkovac. Meanwhile 5414 Azvirt from Azerbaijan is preparing the Ljig to Preljina stretch of the highway, with the €300 million work being financed by Azerbaijan. The Serbian Government is asking China’s Exim Bank for a long term loan of €850 million, of which €300 million would be for the Corridor 11 project and €550 million would be for the Moravski Corridor. Work on the new highway on the Belgrade-Montenegro border will commence in Spring 2013. The Lajkovac to Ljig section will see work start in the near future. Five Chinese contractors have shown interest in the project along with other foreign companies. One offer has come from a Chinese company for a 50km section of the Corridor 11 highway, which could be through either a concession, or a public-partnership model. This section of the highway will connect Ub-Lajkovac and Obrenovac-Ub and was submitted at the beginning of September 2012. A feasibility study has yet to be carried out and this will provide an estimate for the cost of the project, while any concession package would be expected to last from 20-30 years.

For more information on companies in this article

Related Content

  • Serbia road funding being delivered
    January 3, 2017
    A loan of €178 million will pay for the Surcin-Obrenovac highway project in Serbia. The loan for the work is being provided by China’s Export-Import Bank. The financing deal has been agreed between the Serbian Government and the Chinese bank. When Chinese sources deliver funding for road projects, a usual stipulation of the agreement is that the main contracting work should be carried out by a Chinese firm. However, the names of the company or companies that will be involved in the road construction have ye
  • Delay for major Serbian highway project
    August 19, 2016
    Construction work on Serbia’s Ljig-Preljina highway, the Corridor 11 Project, is being delayed. The delay has been caused by complications involving the construction of the tunnel and bridge sections. The construction work is being carried out by the Azerbaijan contractor Azvirt, with local firms carrying out sub-contracting projects. The new route is expected to open around 40 days later than originally expected as a result. Meanwhile the improving political relations between Serbia and its neighbour Ko
  • Construction of Serbia’s Corridor 10 highway on-track
    August 14, 2014
    Construction work on the Lajkovac-Ljig and Obrenovac-Ub sections of Serbia’s Corridor 10 highway are said to be on-track. The stretch will be completed by April 2017 and when the section opens to traffic, it will help reduce journey times with the drive from Belgrade to Zlatibor taking just 90 minutes. He said that delays on the road are not expected. The project value has not been disclosed.
  • Serbia projects due for completion
    December 14, 2016
    Work is pushing ahead with the construction of the Corridor 10 and Corridor 11 highway projects in Serbia. Sections of the highway projects will be opened to traffic in 2017. All of Corridor 10 will be ready for use while the Obrenovac to Preljina stretch of Corridor 11 will open. Other road projects will commence including links running through Moravski and Fruskogorski. The Serbian Government doubled its infrastructure spending to €608.14 million for 2016, with a substantial portion being provided through