Skip to main content

Polish road dispute

A string of legal and political battles look likely in the aftermath of a broken highway contract in Poland.
February 28, 2012 Read time: 2 mins
A string of legal and political battles look likely in the aftermath of a broken highway contract in Poland. A Chinese led consortium headed by China Overseas Engineering Group (2487 COVEC) had been working on a contract for a 50km section of the A2 highway between Lodz and capital Warsaw. The initial award of the contract to COVEC was highly controversial with accusations from other firms tendering for the work that they were unable to compete with the extremely low bid offered by the consortium.

However, COVEC has now broken the original contract agreed with the Polish General Directorate for National Roads and Motorways (1361 GDDKiA). COVEC said it pulled out of the project due to a dispute with GDDKiA over payment deadlines and the unexpected increase in costs for materials.

An official response from GDDKiA has yet to be received. Disputes concerning payments to subcontractors by COVEC are also in hand. It is thought that GDDKiA has been carrying out talks with COVEC over possibly resuming the construction work but under different terms than before, with changes to allow for factors such as the increase in materials prices. It remains to be seen whether GDDKiA will award contracts for portions of the project to firms that submitted tenders in the initial bidding round, which would also allow construction work to recommence. The road does have to be complete for the Euro 2012 football event and GDDKiA is working within a tight schedule to ensure that the section of the A2 between Lodz and Warsaw will be open to traffic in time.

For more information on companies in this article

Related Content

  • Polish Via Carpathia section attracts 11 bids
    July 17, 2020
    Turkish contractor Kolin Insaat has submitted the lowest bid.
  • Deals signed to construct Polish highway project
    August 22, 2017
    Construction of a stretch of the S7 dual carriageway in Poland will commence shortly following the signing of contracts for the work. The stretch, connecting Lotnisko junction with Grojec's ring road, will cost €186.66 million to build. Three contracts were awarded by the Polish General Directorate for National Roads and Motorways (GDDKiA) for the work. Rubau Polska will build a 7km section while a 14.8km stretch will be built by IDS-Bud and Mota-Engil Central Europe will build an 8km portion of the link.
  • Italian firm handling Polish contract
    December 14, 2017
    In Poland a road contract worth some €103.74 million will be carried out by Italian firm Impresa Pizzarotti. The project is for a section of the S61 dual carriageway between Lomza Zachod junction and Kolno junction. The tender process was handled by the Polish road authority, GDDKiA.
  • Polish tunnel opening to traffic
    July 5, 2023
    The Polish Swina tunnel is opening to traffic.