Skip to main content

Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Germany's advanced bridge construction
    February 24, 2012
    The A98 single-lane motorway in Germany is being extended by a second pair of lanes. Work began in 2007 and required building a second bridge at Rheinfelden in the south-west of the country, parallel to the existing bridge, and identical in design and construction.
  • Bridges and tunnels tackle congestion problems
    February 29, 2012
    In preparation for the 2014 Olympic Winter Games, the Black Sea health resort of Sotschi, Russia, is tackling its growing traffic jam problems.A 13km bypass and a new main road passing mainly under the city involves the construction of 15 tunnels and a number of bridges and flyovers.
  • PERI’s VARIOKIT as cantilever equipment takes to bauma stage
    January 6, 2017
    PERI’s VARIOKIT engineering construction kit, being showcased at bauma, is said by the German firm to have already provided cost-effective and flexible solutions for superstructures for several years. From project-specific solutions for tunnels, to system applications in bridge construction and heavy-duty towers for the highest loads, VARIOKIT is extremely adaptable. Now it can also be used for the balanced cantilever method with a few additional, newly developed system components. The new components for t
  • PERI’s VARIOKIT as cantilever equipment takes to bauma stage
    February 13, 2013
    PERI’s VARIOKIT engineering construction kit, being showcased at bauma, is said by the German firm to have already provided cost-effective and flexible solutions for superstructures for several years. From project-specific solutions for tunnels, to system applications in bridge construction and heavy-duty towers for the highest loads, VARIOKIT is extremely adaptable. Now it can also be used for the balanced cantilever method with a few additional, newly developed system components. The new components for t