Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Bridge uses new forming carriage
    February 7, 2012
    The Holzmatttal Bridge for the A98 autobahn in southern Germany stretches 410m across the valley, and on this build the newly-developed Doka forming carriage TU is said to have demonstrated precisely how it drives progress with extremely short cycle times and speedy forming and stripping out operations. The underslung carriage also permits unobstructed access for site traffic.
  • Innovative new drainage solutions will help keep roads free from water
    October 2, 2014
    An array of new technologies will help optimise road drainage and minimise flooding risks - Mike Woof reports In the UK the specialist contractor Lanes Group has carried out extensive inspection work of the drainage systems for the M6 toll route around the city of Birmingham. A powerful zoom camera has been used to carry out the inspection work for Midland Expressway, which operates and maintains the 43km-long motorway, running from Coleshill to Cannock.
  • E-Z Drill highlights 210B-2 on-grade drills at ConExpo 2014
    January 29, 2014
    E-Z Drill’s 210B-2 on-grade drills are being showcased at ConExpo 2014. Part of the 210B Series of on-grade concrete drills and like the 210B model, the 210B-2 is a pneumatic and easy-to-position unit that drills to a standard 45.72cm depth. Both the 210B and 210B-2 drills feature a compact frame, allowing each to operate within a confined area. The units have been specifically designed for straight-line drilling on a level subgrade, and are said to be ideal for airport work, lane additions and large patchw
  • Geosynthetic drainage technology developments
    June 13, 2012
    An innovative solution to providing vital, low-impact surface water control for one of Britain’s largest local authority road schemes is said to have been recently achieved using Hydro International’s (HI) Hydro Vortex Drop Shaft  ow control technology. The new 7km bypass built by Costain at Church Village, near Pontypridd, South Wales, required careful planning to minimise its effect on the countryside and the local environment. Rhondda Cynon Taff Council needed to bypass Church Village to reduce traf c