PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen
  • Contracts are about to be signed for the Fehmarnbelt Fixed Link
    March 13, 2015
    Nearly eight years after Denmark and Germany agreed to construct a major undersea road and rail tunnel, the first contracts are about to be signed. David Arminas reports. Construction is due to start later this year on one of Europe’s most ambitious, as well as the world’s longest, road and rail tunnels, the 17.6km Fehmarnbelt Fixed Link between Germany and Denmark. Fehmarnbelt is expected to cost around US$7.5 billion and be five times the length of the Øresund tunnel between the Danish capital Copenhagen
  • Major bridge widening project going to plan
    May 2, 2012
    When built it was determined that a vital US road/rail bridge would always be widened.
  • Major bridge widening project going to plan
    April 11, 2012
    When built it was determined that a vital US road/rail bridge would always be widened. Work on that huge project is going to plan as Patrick Smith reports One of the biggest bridge widening projects in the world is being carried out under an ambitious development programme. At US$1.2 billion, the seven-year scheme to widen the Huey P. Long Bridge in the US state of Louisiana is also the largest of 16 projects planned under the state's TIMED (Transportation Infrastructure Model for Economic Development)