Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Next-generation materials testing with new technology
    August 17, 2022
    The US’s Balanced Mix Design sets the stage for next-generation performance testing, according to CONTROLS’ Andrea Carlessi
  • Manitowoc cranes construct Portugal's tallest viaduct
    April 16, 2012
    Five Potain cranes were used to build pylons for the Viaduto do Corgo project in Portugal. The recently completed 2.8km viaduct is one of the longest and tallest in the country. The machines were supplied by Manitowoc's Portugal office on a rental contract, who managed the cranes throughout the project. In addition to installing the cranes, the local Manitowoc Crane Care team also climbed and relocated the cranes as work progressed. Each crane worked with a 45m jib and constructed four pylons at a time. In
  • Canadian air
    February 8, 2012
    Compressors from Atlas Copco are proving highly useful in highly diverse applications, on a bridge project and a quarry in Canada. Water ingress over 30 years has damaged a road bridge in Quebec City, Canada, deteriorating the concrete and breaking down the rubber expansion joints at both ends of the 150m long structure. City highway authority, Transportes Quebec, awarded local contracting company Inter-Structures the contract to replace the deteriorated concrete and fit new membrane seals. The bridge, clos
  • Dragados among six in the running for fourth Panama bridge deal
    August 23, 2016
    All six consortia that submitted documents in May to design and build a fourth bridge over the Panama Canal have pre-qualified, according to media reports. The companies officially vying for the estimated US$1 billion contract are: • Dragados • Consorcio CCB: Constructora Norberto Odebrecht, Odebrecht Engenharia e Construcao International • Consorcio Hyundai, Sacyr JV • Consorcio Astaldi – Daelim • Consorcio Panamá Cuarto Puente: China Communications Contruction Company, China Harbour Engi