PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Nigeria’s giant city Lagos to benefit from a new cable-stayed bridge
    September 19, 2012
    The first cable-stayed bridge in Nigeria will link two districts of the megacity of Lagos Nigeria’s first cable-stayed bridge, the Lekki Ikoyi Bridge in the megacity of Lagos is scheduled for completion at the end of 2012. Its striking 90m high pylon characterises the appearance of the 1,357m long bridge, which will connect two districts of the West African city, Lekki on the Lekki Peninsula and Ikoyi on Lagos Island.
  • Bridge project uses high performing formwork
    February 20, 2012
    Doka designed and supplied a high-performing formwork technology solution for a challenging bridge project south of the German town of Halle. The 8,614m long single-cell box girder superstructure of the Saale-Elster Viaduct, with a typical cross section width of 13.9m, is borne on 220 piers, and has a constructional depth of 4m. It is mainly being erected on launching girders to minimise the impact on flora and fauna.
  • Peri climbs high at INTERMAT 2015 with its civil engineering technology
    January 6, 2017
    Peri’s Variokit heavy-duty truss girder system has been designed specifically for tunnel and bridge construction to reach those hard-to-get places. The heavy-duty truss girder complements the Variokit heavy-duty shoring tower. Peri took into account the load-bearing capacity of the tower as well as the challenging requirements of everyday construction work.
  • Peri climbs high at INTERMAT 2015 with its civil engineering technology
    April 24, 2015
    Peri’s Variokit heavy-duty truss girder system has been designed specifically for tunnel and bridge construction to reach those hard-to-get places. The heavy-duty truss girder complements the Variokit heavy-duty shoring tower. Peri took into account the load-bearing capacity of the tower as well as the challenging requirements of everyday construction work.