Polish debut

PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów. Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met. Twelve pairs of piers support the two carriageways of the new motorw
July 20, 2012 Read time: 2 mins
298 PERI has used its cantilever-construction compatable VARIOKIT for the first time in Poland. The engineering build kit was used to build a new 600m long motorway bridge near the southeastern city of Tarnów.

Deploying VARIOKIT allowed the jobsite team to achieve 4-5 day cycles for the bridge's  concrete sections. It was also said to ensure that the very small tolerances needed for the variable bridge cross-sections could be comfortably met.

Twelve pairs of piers support the two carriageways of the new motorway bridge, each of which is 13m wide. Falsework carried the formwork for the hollow box superstructure of the foreland bridges - consisting of girder wall formwork elements and high load-bearing GT 24 lattice girders. Depending on the support height and load different PERI shoring was used, including ST 100 stacking towers as well as shoring towers on the basis of frame-connected MULTIPROP slab props.

Meanwhile, the near 210m long section between the seventh and the 10th piers was achieved in 48 casting segments using the balanced cantilevered method. For this, contractors 4761 Dragados used four cantilever construction units based on VARIOKIT.

For more information on companies in this article

Related Content

  • Hats off to Polypipe
    May 15, 2020
    Ridgidrain allows pipe sections to be cut without affecting pipe integrity.
  • Utility machine innovations coming to market
    December 1, 2022
    A wide array of new items of compact utility equipment are coming to market, with low emissions and noise as key machine trends
  • Istanbul’s new airport benefits from Wirtgen Group machines
    November 22, 2017
    Construction of Istanbul’s new airport facility is benefiting from the use of a large fleet of machines from the Wirtgen Group. When it is complete, this will be the world’s largest airport and will be able to handle 150-200 million passengers/year as well as 6 million tonnes of freight/year. This will make the facility substantially larger than the world’s current largest airport, the Hartsfield-Jackson Atlanta International Airport, which handles around 105 million passengers/year.