Poland: GDDKiA sets winter road maintenance budget

Poland’s General Directorate for National Roads and Motorways (GDDKiA) is planning to spend US$151.37 million (€118.3 million) on winter-specific road maintenance for 2014/15. Around 2,300 snowploughs and 1,300 salt trucks will be readied for winter work. GDDKiA also plans to install more than 1,400km snow-protection screens along roads. Meanwhile, the country is moving ahead with several key highway projects, one involving construction of three sections of the new southern ring road around the Polish c
October 22, 2014 Read time: 2 mins
Poland’s General Directorate for National Roads and Motorways (1361 GDDKiA) is planning to spend US$151.37 million (€118.3 million) on winter-specific road maintenance for 2014/15.

Around 2,300 snowploughs and 1,300 salt trucks will be readied for winter work. GDDKiA also plans to install more than 1,400km snow-protection screens along roads.

Meanwhile, the country is moving ahead with several key highway projects, one involving construction of three sections of the new southern ring road around the Polish capital Warsaw. Building the 18.5km that comprises the three sections is expected to cost nearly $2.03 billion (€1.6 billion).

Also planned is construction of three sections of the S6 express road totalling just over 54km from Goleniow near Szczecin to Koszalin. GDDKiA expects that each section will take up to 37 months to complete. The entire project will cost an estimated $909 million (€718.4 million).

Other planned works are for the $216.5 million (€171 million) Rzeszow to Jaroslaw section of the A4 highway and the $130.4 million (€103 million) S8 dual carriageway between Warsaw and Bialystok.

For more information on companies in this article

Related Content

  • Poland: Budimex signs Olsytyn city ring-road contract
    April 4, 2016
    Budimex has signed a contract worth more than €214.3 million for construction of the second section of Olsztyn's ring-road. The section will be around 14.7km long and will be completed within 28 months. The bid by Budimex was the fourth lowest offer in the tender, as announced by the Polish General Directorate for National Roads and Motorways (GDDKiA).
  • Deals signed to construct Polish highway project
    August 22, 2017
    Construction of a stretch of the S7 dual carriageway in Poland will commence shortly following the signing of contracts for the work. The stretch, connecting Lotnisko junction with Grojec's ring road, will cost €186.66 million to build. Three contracts were awarded by the Polish General Directorate for National Roads and Motorways (GDDKiA) for the work. Rubau Polska will build a 7km section while a 14.8km stretch will be built by IDS-Bud and Mota-Engil Central Europe will build an 8km portion of the link.
  • Poland to boost high-speed road construction in 2017
    January 24, 2017
    Poland plans to issue a number of major highway construction tenders early this year as part of plan to boost the number of high-speed road projects started in 2017. Around €4.84 billion be spent this year on road construction and maintenance. Expected to be on offer is the missing A1 section between Tuszyn and Czestochowa as well as construction of an S61 dual carriageway from Ostrowia Mazowiecka to Szczuczyn. Polish media reported that around 124km of dual carriageways and motorways were built last
  • Mostostal Warszawa picked for S19 segment
    August 11, 2022
    The contract in northern Poland is worth around €211 million.