Performance-based contracts are the way forward World Bank expert tells PPRS Paris 2015

There “will never be sufficient funds for all planned road activities” says Ben Gericke, transport specialist at The World Bank. The road maintenance industry is going to have to use the best possible contract strategy to win the investment it needs. Speaking at the PPRS Paris 2015 pavement preservation and recycling summit, Gericke said that the best way for the global highway construction and road maintenance sector was to get its fair share of any national spending plan was to turn to performance-based c
February 27, 2015 Read time: 4 mins
There “will never be sufficient funds for all planned road activities” says Ben Gericke, transport specialist at The World Bank. The road maintenance industry is going to have to use the best possible contract strategy to win the investment it needs.

Speaking at the PPRS Paris 2015 pavement preservation and recycling summit, Gericke said that the best way for the global highway construction and road maintenance sector was to get its fair share of any national spending plan was to turn to performance-based contracts. Highway authorities increasingly need to reassure their funding partners that they were getting value for money.

He is convinced that the secret of success is to “deliver good asset management in the road sector through performance-based contracting (PBC).” Why? Because market research and experience at The World Bank have both shown that this is the best way forward.

According to Gericke, “a World Bank Review in the late eighties recommended that bank projects should outsource both works and consultancy services based on the perceived value for money gained when compared to in-house activities.” The “contracting methodology was based on FIDIC Red Book (and) in the 1990s several countries commenced with performance-based maintenance contracting.”

The results were positive and today more and more governments have turned to performance-based contracting. And, as the years have gone by, “contracting methodology has developed to include the initial improvement and rehabilitation works as part of PBC,” says Gericke. He told PPRS Paris 2015 that the “latest OPRC (output and performance-based road contracts now follow a design-build-operate-maintain-transfer” approach.

In 2011 2332 World Bank reviewed the use of OPRC to develop guidance on the use of the different approaches and the lessons learned were “a significant improvement in value for money and general savings of between 10-40% when compared to traditional contracts.” Gericke also believes that the PBC approach leads to “improved understanding of asset management principles (and better) levels of service.” PBC contracting has also “reduced administration costs with a smaller number of contracts.” There is also “reduced opportunities for corruption, as construction risk is transferred to the contractor.” The World Bank has also noticed that “improved workmanship as a result of the contractor being financially liable for defects.”

The end result is “a more consistent level of service being delivered to the road user,” Gericke argues, and “a better focus on innovation and the sharing of risk.” The challenges include making sure you identify all the risks upfront, that the correct payment model is in place and that all parties involved have agreed what the minimum levels of  service should be.”

The process is robust too. “Very few PBCs fail once implemented …although not all deliver the full benefits initially realised),” says Gericke. “Most ‘failures’ of PBC are actually situations where the implementation did not occur at all.” To make it work, “a sound understanding of risk, the allocation of risk and the definition of risk boundaries is essential (and) to make it through the full PBC process, the project requires strong champions in the road agency, the ministry of finance and the bank or other lending institution.”

Be flexible too. “The existing sample OPRC bidding documents seldom get used without substantial change,” says Gericke, and “procurement of PBC – both for consultant support and the physical works – on a lowest price basis is not in the best interest of the PBC.” He worries that “road authorities often struggle to recognise the value-for-money PBCs and good asset management have to offer.”

Agreeing what a successful outcome will look like before you start, is also important. “The retention of asset value is a key challenge,” Gericke warns. “How will the end-of-contract road condition be defined and measured?”

With most OPRC contracts, the road owner is paying for a service to be provided and the contractor has to ensure that the road user gets a certain level of service. This level of service is often defined in terms of usability, travel speeds, road surface conditions, safety features, roadside assistance, and so on. Specifications included in a typical contract could include describing the level of service expected for every road in the network.

A number of studies have shown that the supervision of performance-based contracts is very different from the traditional way in which a project was supervised because a PBC project usually focuses on fewer performance criteria. It is also much cheaper to supervise a PBC scheme … instead of 7-10 % of the contract value, it will only be around 3-5 %. For a network of 450 km, supervision should not take more than 3 to 4 days every month.

Contractors like PBC projects because they get paid a fixed monthly amount if they meet the agreed performance criteria, and usually they are free to decide what to do, as well as when, where and how.

For more information on companies in this article

Related Content

  • Highways England: new agency with long-term investment strategies
    August 18, 2015
    Highways England, created out of the old Highways Agency, was set up on April 1 to oversee a closer relationship between government client and private contractors. World Highways went to a recent forum in London to hear both sides declare their hopes and challenges. Government reforms are often met with a certain amount of scepticism thanks to years of disillusionment over forgotten ministerial promises. Given that, highway contractors in the UK could have been forgiven if they had raised their eyes skyward
  • A macro website launched for microsurfacing processes
    October 9, 2018
    RoadResource.org as a go-to website for surfacing information is now live When RoadResouce.org went live – quietly - in July it was the end of two years of hard work by three major US associations for pavement preservation. But there was no grand party or ceremonial pushing of the “go live” button, says Doug Hogue, vice president and general manager of VSS Macropaver. “For all of us in the industry July is a busy period that left little time to celebrate on the opening day,” says the 51-year-old chartere
  • Book now … the early booking deadline for PPRS 2015 in Paris has been extended
    November 13, 2014
    Book now … the first Pavement Preservation &-Recycling (World) Summit (PPRS 2015), due to take place in the Palais des Congrès in Paris from February 22 2015 to February 25 2015, has extended its deadline for early bird registration November 15 2014.
  • Engineering agreement for international collaboration
    July 18, 2019
    A new agreement has been reached that will foster more cooperation and collaboration with regard to engineering at an international level. The International engineering federation FIDIC (the International Federation of Consulting Engineers) has signed a memorandum of understanding (MoU) with the China International Contractors Association (CHINCA). This move is intended to improve collaboration between international and Chinese businesses, facilitate skills and knowledge transfer and increase the unders