Performance-based contracts are the way forward World Bank expert tells PPRS Paris 2015

There “will never be sufficient funds for all planned road activities” says Ben Gericke, transport specialist at The World Bank. The road maintenance industry is going to have to use the best possible contract strategy to win the investment it needs. Speaking at the PPRS Paris 2015 pavement preservation and recycling summit, Gericke said that the best way for the global highway construction and road maintenance sector was to get its fair share of any national spending plan was to turn to performance-based c
February 27, 2015 Read time: 4 mins
There “will never be sufficient funds for all planned road activities” says Ben Gericke, transport specialist at The World Bank. The road maintenance industry is going to have to use the best possible contract strategy to win the investment it needs.

Speaking at the PPRS Paris 2015 pavement preservation and recycling summit, Gericke said that the best way for the global highway construction and road maintenance sector was to get its fair share of any national spending plan was to turn to performance-based contracts. Highway authorities increasingly need to reassure their funding partners that they were getting value for money.

He is convinced that the secret of success is to “deliver good asset management in the road sector through performance-based contracting (PBC).” Why? Because market research and experience at The World Bank have both shown that this is the best way forward.

According to Gericke, “a World Bank Review in the late eighties recommended that bank projects should outsource both works and consultancy services based on the perceived value for money gained when compared to in-house activities.” The “contracting methodology was based on FIDIC Red Book (and) in the 1990s several countries commenced with performance-based maintenance contracting.”

The results were positive and today more and more governments have turned to performance-based contracting. And, as the years have gone by, “contracting methodology has developed to include the initial improvement and rehabilitation works as part of PBC,” says Gericke. He told PPRS Paris 2015 that the “latest OPRC (output and performance-based road contracts now follow a design-build-operate-maintain-transfer” approach.

In 2011 2332 World Bank reviewed the use of OPRC to develop guidance on the use of the different approaches and the lessons learned were “a significant improvement in value for money and general savings of between 10-40% when compared to traditional contracts.” Gericke also believes that the PBC approach leads to “improved understanding of asset management principles (and better) levels of service.” PBC contracting has also “reduced administration costs with a smaller number of contracts.” There is also “reduced opportunities for corruption, as construction risk is transferred to the contractor.” The World Bank has also noticed that “improved workmanship as a result of the contractor being financially liable for defects.”

The end result is “a more consistent level of service being delivered to the road user,” Gericke argues, and “a better focus on innovation and the sharing of risk.” The challenges include making sure you identify all the risks upfront, that the correct payment model is in place and that all parties involved have agreed what the minimum levels of  service should be.”

The process is robust too. “Very few PBCs fail once implemented …although not all deliver the full benefits initially realised),” says Gericke. “Most ‘failures’ of PBC are actually situations where the implementation did not occur at all.” To make it work, “a sound understanding of risk, the allocation of risk and the definition of risk boundaries is essential (and) to make it through the full PBC process, the project requires strong champions in the road agency, the ministry of finance and the bank or other lending institution.”

Be flexible too. “The existing sample OPRC bidding documents seldom get used without substantial change,” says Gericke, and “procurement of PBC – both for consultant support and the physical works – on a lowest price basis is not in the best interest of the PBC.” He worries that “road authorities often struggle to recognise the value-for-money PBCs and good asset management have to offer.”

Agreeing what a successful outcome will look like before you start, is also important. “The retention of asset value is a key challenge,” Gericke warns. “How will the end-of-contract road condition be defined and measured?”

With most OPRC contracts, the road owner is paying for a service to be provided and the contractor has to ensure that the road user gets a certain level of service. This level of service is often defined in terms of usability, travel speeds, road surface conditions, safety features, roadside assistance, and so on. Specifications included in a typical contract could include describing the level of service expected for every road in the network.

A number of studies have shown that the supervision of performance-based contracts is very different from the traditional way in which a project was supervised because a PBC project usually focuses on fewer performance criteria. It is also much cheaper to supervise a PBC scheme … instead of 7-10 % of the contract value, it will only be around 3-5 %. For a network of 450 km, supervision should not take more than 3 to 4 days every month.

Contractors like PBC projects because they get paid a fixed monthly amount if they meet the agreed performance criteria, and usually they are free to decide what to do, as well as when, where and how.

For more information on companies in this article

Related Content

  • UK’s M6 tolled motorway for sale
    June 21, 2016
    For sale: one UK toll motorway along with operating business. Well maintained. Price negotiable. David Arminas looks at what is on offer As if right on cue, a French articulated truck starts to back up along the hard shoulder at an exit area of M6toll. The manoeuvring is watched from an office inside the nearby M6toll headquarters. Inside, Andy Pearson, chief executive of M6toll, glances over his shoulder and interrupts his presentation to World Highways. “He’s probably missed the dedicated wide-load
  • New M90 surfacing in the UK gain praise
    January 8, 2013
    Early evaluation of surfacing work on the M90 at Rosyth – the first major application of Scotland’s new TS2010 specification – has earned positive praise. Transport Scotland’s determination to obtain pavement that is durable, long lasting and safe (especially in early life) is clearly apparent on the M90 just north of the Forth Road Bridge. Here surfacing has been carried out this spring to TS2010, a tough new specification designed to ensure thin surfacing pavements that work. And the initial prognosis is
  • The radically changing face of UK highways management
    May 14, 2014
    The British Government policy paper ‘Action for Roads: A network for the 21st century’ sets out radical change to the strategic way roads are funded and managed – including plans to turn the Highways Agency into a Government-owned company and a pledge to invest over €33.4 billion (£28 billion) in roads maintenance between 2015 and 2020. Jenny Moten, Highways Agency divisional director for Network Services, gave a keynote presentation on the new approach to strategic highways management during the Road Safet
  • CECE Congress focuses on future of construction
    April 10, 2012
    The bi-annual CECE Congress was held in Spain when participants looked forward in a bid to see what will happen in the next ten years Growth markets such as China, India and Brazil offer big opportunities to European construction equipment manufacturers. As companies, particularly those from China, start to expand outside their own countries the competition for business will increase, and it has been claimed that there is no such thing as 'the global market', rather it is the sum of hundreds, if not thousa