New Zealand’s ‘Roads of national significance programme’ to end 2024?

New Zealand Transport Agency (NZTA) has told Transport Minister Gerry Brownlee that the completion of the government's roads of national significance programme might be pushed to 2024, as certain key motorway projects could take up to three years longer than anticipated. Under the NZ$9 billion (US$6.92 billion) plus programme, NZ$2.40 billion will be used for the Waikato Expressway; followed by another $2 billion for Auckland Western Ring Route including Waterview Connection; $1.76 billion for the highway b
June 19, 2012 Read time: 1 min
1009 New Zealand Transport Agency (NZTA) has told Transport Minister Gerry Brownlee that the completion of the government's roads of national significance programme might be pushed to 2024, as certain key motorway projects could take up to three years longer than anticipated.

Under the NZ$9 billion (US$6.92 billion) plus programme, NZ$2.40 billion will be used for the Waikato Expressway; followed by another $2 billion for Auckland Western Ring Route including Waterview Connection; $1.76 billion for the highway between Puhoi and Wellsford; and $1 billion for Wellington motorways including Transmission Gully.

The government will also spend $730 million for Christchurch motorways and $ 500million for Tauranga Eastern Corridor. About $400 million was spent on the completed Victoria Park link.

In February 2012, NZTA told the minister that the body is committed to significantly completing the seven roads by 2020/2021, subject to the availability of funding.

For more information on companies in this article

Related Content

  • Machinery moves on site for New Zealand’s Kapiti Coast expressway
    July 11, 2017
    Onsite work has started in the Kapiti Coast region on the Otaki-Peka Peka Expressway, part of the greater Wellington Northern Corridor project. Simon Bridges, New Zealand’s transport minister, recently turned the first sod on the US$175 million project. Travel times should be improved between Port of Wellington, hospitals, Wellington’s central business district and ferry terminals. The 110km Wellington Northern Corridor largely follows the current state highway route from the airport to Linden, near Tawa. F
  • New Zealand busway project
    November 10, 2021
    Work is now going ahead for the busway project for Auckland in New Zealand.
  • Causeway project for New Zealand city Auckland
    February 12, 2014
    Work is underway on the Causeway Upgrade Project in New Zealand. The US$183.3 million (NZ$220 million) contract was awarded by the New Zealand Transport Agency (NZTA). The route forms part of State Highway 16, with the fork being part of Auckland's Western Ring Route. The contract was awarded to the Causeway Alliance, a consortium made up of Aecom, Coffey Geotechnics, Fulton Hogan, Leighton Contractors, Sinclair Knight Merz and the NZTA.
  • Procurement open for Northland Corridor
    March 26, 2025
    The Ara Tūhono/Warkworth-to-Te Hana section in New Zealand is the most advanced part of the corridor in terms of consents, property acquisition and design.