New bridge link under construction in Ohio

Construction work is proceeding on track with the erection of a new bridge over the Ohio River in the US. Building work on this US$81 million project began in March 2012 and is expected to be completed by 2015. Brayman Construction Corporation is building the new Ironton-Russell Bridge, which will replace an existing structure spanning the Ohio River. Finley Engineering Group is providing bridge construction engineering services to Brayman Construction Corporation for the project, which will provide a link
June 21, 2012 Read time: 2 mins
Construction work is proceeding on track with the erection of a new bridge over the Ohio River in the US. Building work on this US$81 million project began in March 2012 and is expected to be completed by 2015. 5978 Brayman Construction Corporation is building the new Ironton-Russell Bridge, which will replace an existing structure spanning the Ohio River.

5979 Finley Engineering Group is providing bridge construction engineering services to Brayman Construction Corporation for the project, which will provide a link between Second and Jefferson streets in downtown Ironton and the US 23 viaduct south of Russell.

The project also includes demolition of the existing bridge upon completion of the new structure. The new bridge was originally scheduled to be built in 2007 but the date was pushed back to 2013 due to State funding issues. Finley provided pre-bid engineering services which included development of a construction sequence that will cast the back spans on falsework. The falsework system can support all construction equipment required for the pylons and deck, minimising the need for marine operations.

Additionally, FINLEY designed an innovative precast stay anchor block system that will simplify stay cable anchorage placement, speed up segment construction and simplify the form traveler system by eliminating the need for a temporary stay anchorage.

For more information on companies in this article

Related Content

  • Work on St Petersburg bridge project
    June 20, 2016
    Contractor ICA Construction used two Aquajet robotic hydrodemolition machines at the top of a 120m-high bridge pylon located in the city of St Petersburg. The two Aquajet robotic water cutters were used to remove surplus concrete from around the inner steel structure of the bridge pylon. This link spans the River Neva and forms part of the Western High-Speed Diameter (WHSD) route in St Petersburg. The WHSD is a highly important route for the region and will provide a key connection between the Scandinavi
  • New bridge under construction in Turkey
    March 28, 2014
    Work is underway on a new bridge structure in Turkey, with tower cranes playing a key role in the project The two Potain tower cranes are being used to build a 610m long cable-stayed bridge in the south-east of the country. The two cranes are MC235B models and are working 10 hours/day on the project, which is taking 30 months. The new bridge will provide an important connection across the Ataturk Dam Reservoir on the Euphrates River.
  • UK motorway bridge work
    June 10, 2025
    A new bridge now spans the UK’s busy M6 motorway.
  • Emovis continues with Mersey Gateway tolling
    March 18, 2022
    Emovis provides collection of tolls and charges for both Mersey Gateway Crossing and the older 87m-long Silver Jubilee Bridge through its merseyflow brand name.