Missouri’s Blanchette Bridge gets smaller and smaller

Missouri’s Blanchette Bridge is now even more abridged. Just a few weeks after explosives took out the West Struss Span, the remaining steel truss on the bridge’s westbound lanes was blown up by demolition crews on Tuesday December 5, 2012. More than 2,000tonnes of steel dropped over 300m into the Missouri River. A 107m section of the Blanchette Bridge was brought down last month. The Blanchette Bridge blasting is part of a US$63 million, year-long project to replace the westbound span.
December 10, 2012 Read time: 1 min
Missouri’s Blanchette Bridge is now even more abridged.

Just a few weeks after explosives took out the West Struss Span, the remaining steel truss on the bridge’s westbound lanes was blown up by demolition crews on Tuesday December 5, 2012.

As a result of the latest explosion over 300m of steel, weighing more than 2,000tonnes, dropped into the Missouri River.

A 107m section of the Blanchette Bridge was brought down last month.

The Blanchette Bridge blasting is part of a US$63 million, year-long project to replace the westbound span.

%$Linker: 2 External <?xml version="1.0" encoding="utf-16"?><dictionary /> 0 0 0 oLinkExternal The bridge that keeps getting smaller www.demolitionnews.com false http://www.demolitionnews.com/2012/12/04/video-the-bridge-that-keeps-getting-smaller/ false false%>

Related Content

  • Loadrite introduces its 360° load-out management system
    April 18, 2013
    The new Loadrite 360° management system has been designed to boost efficiency in quarries by integrating communication across all stages of an order for faster turnarounds and maximised payloads. Loadrite said that the system improves communication throughout the load-out operations. It is aimed at providing quarry managers with the tools they need to get the most from both staff and equipment. Benefits include lower costs per tonne and optimised truck utilisation, said the company.
  • High court drama expected at Highways UK event, NEC, Birmingham
    November 7, 2016
    What happens when a highways services employee is prosecuted for failing to follow established safety procedures? How would a courtroom drama unfold for the accused and the employer?
  • Putzmeister adds five-section pump
    January 6, 2017
    Putzmeister has added a five-section 38m, 160m3/hr concrete pump, which can be used to place loads inside buildings some 3m higher than the four-section option. Built on a 26tonne chassis, the new 38.5 can reach heights of 31m while leaving the final boom section to pass inside the building. In common with the company’s other machines, the 38.5 now has outrigger sensing, which feeds into the control system and prevents the boom from extending/slewing if the outriggers are not fully deployed. The machine als
  • Putzmeister adds five-section pump
    April 19, 2013
    Putzmeister has added a five-section 38m, 160m3/hr concrete pump, which can be used to place loads inside buildings some 3m higher than the four-section option. Built on a 26tonne chassis, the new 38.5 can reach heights of 31m while leaving the final boom section to pass inside the building. In common with the company’s other machines, the 38.5 now has outrigger sensing, which feeds into the control system and prevents the boom from extending/slewing if the outriggers are not fully deployed. The machine als