Skip to main content

Mersey Gateway: Consortia Talks

The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
April 4, 2012 Read time: 3 mins
RSSThe competitive dialogue phase of the Mersey Gateway Project has begun.

The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months.

The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013.

The value of the construction phase of the project, including land, is estimated at US$961million.

Councillor Rob Polhill, Leader of Halton Borough Council, said: “The rest of this year will be critical in shaping the final detail of the bidders’ proposals, and we will be working closely with each bidding group to ensure that we are able to maintain quality on this project whilst continuing to deliver value for money for the public purse.”

Steve Nicholson, Mersey Gateway Project (MGP) director, said: “The quality of the initial submissions was excellent, and I am looking forward to working with each of the bidding groups to enable them to pull together their detailed proposals.”

Last month Halton Borough Council announced the identities of the three shortlisted bidders. They are:

1146 Balfour Beatty, 979 Bouygues Travaux Publics, 2376 EGIS Projects consortium, comprising equity members Balfour Beatty plc, Bouygues Travaux Publics and Egis Projects.

Merseylink consortium, comprising equity members 2378 Macquarie Capital Group Limited, 2516 Bilfinger and Berger Project Investments Limited, Vialia Sociedad Gestora de Concesiones de Infraestructuras S.L. and 1340 FCC Construcción S.A.

MGL consortium, comprising equity members 3932 Galliford Try Investments Limited, 981 Hochtief PPP Solutions GmbH and 3933 Iridium Concesiones de Infraestructuras S.A.

The centrepiece of the MGP is a new six-lane toll bridge over the Mersey between the towns of Runcorn and Widnes.

In addition to speeding up journey times and improving journey reliability in the region, it is intended to act as a catalyst for investment and bring benefits over four times greater than the investment cost.

The benefits are predicted to include the creation of an estimated 4,640 new jobs through direct employment, regeneration activity and inward investment, and the generation of a conservative estimate of $99million a year in Gross Value Added from the new jobs by 2030.

The existing Silver Jubilee Bridge will also be tolled as part of the project.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

As well as the income from tolls, the 5432 Department for Transport will provide $138million in capital grant towards land and remediation and up to $23.3million per year in long-term revenue support for 26.5 years from opening to fund the scheme.

For more information on companies in this article

Related Content

  • Building New zealand's landmark tunnel
    February 15, 2012
    A landmark tunnelling project is commencing in New Zealand - Kristina Smith reports. New Zealand is preparing to embark on its biggest transport project ever. In August it announced that it had selected its preferred bidder for the NZ$1.4 billion Waterview Connection in Auckland, 5km of new motorway connecting highways to the North and South of the city.
  • Brazil launches new transport infrastructure investment plan
    August 30, 2012
    The Brazilian government has announced a new transport infrastructure investment plan involving the concession of motorway operations and modernisation of the railway sector. The private public partnerships are predicted to lead to an investment of US$65.68 billion (BRL 133bn) in the next 25 years, including US$ 39.63 billion (BRL 80bn) to be spent in the first five years of the contract.
  • Solution found for Colombian tunnel project?
    March 12, 2015
    A solution seems to have been found for Colombia’s long-running La Linea Tunnel project. Work has been delayed on the tunnel for a number of reasons and on a number of occasions, most recently due to funding issues. But previous delays were due to such diverse causes as technical challenges posed by the difficult conditions and a lack of suitable insurance cover. The Colombian Government has come to an agreement with the Segundo Centenario consortium building the tunnel that will see construction activity r
  • Balfour included on major UK Highways Agency framework contract
    November 7, 2014
    Balfour wins place on major UK Highways Agency road framework contract Balfour Beatty’s UK construction business has been appointed by the UK’s Highways Agency to a new collaborative framework contract for projects totalling more than US$3.95 billion (£2.5 billion). Under the framework arrangement, Balfour is one of five contractors that the agency can call upon to deliver individual projects worth between $160 million and $713 million (£100 million and £450 million) on Lot 3B of the Collaborative Del