Mersey Gateway: Consortia Talks

The competitive dialogue phase of the Mersey Gateway Project has begun. The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months. The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013. The value of the construction phase of the project, including land, is estimated at US$961milli
April 4, 2012 Read time: 3 mins
RSSThe competitive dialogue phase of the Mersey Gateway Project has begun.

The project team are said to have held initial meetings with the three shortlisted bidding consortia, and will be working closely with each of them over the coming months.

The aim is for each of the three bidders to submit their detailed proposals by the end of 2012, with an announcement about a preferred bidder likely to come in spring 2013.

The value of the construction phase of the project, including land, is estimated at US$961million.

Councillor Rob Polhill, Leader of Halton Borough Council, said: “The rest of this year will be critical in shaping the final detail of the bidders’ proposals, and we will be working closely with each bidding group to ensure that we are able to maintain quality on this project whilst continuing to deliver value for money for the public purse.”

Steve Nicholson, Mersey Gateway Project (MGP) director, said: “The quality of the initial submissions was excellent, and I am looking forward to working with each of the bidding groups to enable them to pull together their detailed proposals.”

Last month Halton Borough Council announced the identities of the three shortlisted bidders. They are:

1146 Balfour Beatty, 979 Bouygues Travaux Publics, 2376 EGIS Projects consortium, comprising equity members Balfour Beatty plc, Bouygues Travaux Publics and Egis Projects.

Merseylink consortium, comprising equity members 2378 Macquarie Capital Group Limited, 2516 Bilfinger and Berger Project Investments Limited, Vialia Sociedad Gestora de Concesiones de Infraestructuras S.L. and 1340 FCC Construcción S.A.

MGL consortium, comprising equity members 3932 Galliford Try Investments Limited, 981 Hochtief PPP Solutions GmbH and 3933 Iridium Concesiones de Infraestructuras S.A.

The centrepiece of the MGP is a new six-lane toll bridge over the Mersey between the towns of Runcorn and Widnes.

In addition to speeding up journey times and improving journey reliability in the region, it is intended to act as a catalyst for investment and bring benefits over four times greater than the investment cost.

The benefits are predicted to include the creation of an estimated 4,640 new jobs through direct employment, regeneration activity and inward investment, and the generation of a conservative estimate of $99million a year in Gross Value Added from the new jobs by 2030.

The existing Silver Jubilee Bridge will also be tolled as part of the project.

It is anticipated that construction work will start within two years, and that the new bridge will take around three years to complete.

As well as the income from tolls, the 5432 Department for Transport will provide $138million in capital grant towards land and remediation and up to $23.3million per year in long-term revenue support for 26.5 years from opening to fund the scheme.

For more information on companies in this article

Related Content

  • San Miguel Corp is among bidders in Cavite-Laguna re-auction
    March 19, 2015
    San Miguel Corporation, Metro Pacific Investments Corporation and an unidentified firm reportedly are bidding in the US$1.25 billion re-auction for work on the Cavite-Laguna Expressway. The deal involves building, operating and maintaining the 47km four-lane toll road for 35 years under a public-private-partnership. The sum includes a $448 million bid price, equal to the premium offered by SMS subsidiary Optimal Infrastructure Development during the first tender for the project in June 2014. San Miguel was
  • Spanish firms interested in US$740mn Chile bridge project
    June 5, 2013
    Spanish companies Sacyr, ACS and OHL will take part in three of the consortia that will bid in the US$740 million contract to build the longest suspension bridge in Chile. Works for the 2.5km Chacao Bridge, connecting the island of Chiloe and Chile's coast line, are expected to be awarded during the first quarter of 2014, with construction due to begin in 2015.
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • New expressway project awarded in China
    March 11, 2019
    The contract for a major new expressway project in China has been won by a consortium. The Guizhou Jianhe-Liping Expressway should cost close to US$1.9 billion to build and take three years to construct. The group handling the work comprises CRRC Kunlun Investment Group Co and divisions of China Railway Construction Corporation Limited (CRCC). The expressway deal includes a 30 year concession to operate the tolled. Link. The project is being handled under the PPP model that includes viable gap funding, equi