Lafarge starts Vancouver YVR runway paving

Lafarge Canada, part of Holcim, is the paving subcontractor for Vancouver Airport’s North Runway Modernisation Programme in British Columbia.
By David Arminas May 13, 2025 Read time: 3 mins
Crews had a trial exercise to refine strategies and safety, given the limited nightly construction window at the airport in British Columbia, Canada (image courtesy Vancouver International Airport/YVR)

Asphalt paving of the Vancouver International Airport’s north runway has begun, with around 150m increments completed each night.

The asphalt lift will finish with a slope grade to allow the safe landing and takeoff of aircraft during the north runway’s daily operating hours, according to airport officials. As part of the paving works, crews are also removing, rising and reinstalling runway lights and reapplying paint markings before the runway is returned to service each day.

Global Highways reported in January that Lafarge Canada, a member of the Holcim Group, had been selected as the paving subcontractor for Vancouver International Airport’s North Runway Modernisation Programme. The company had previously worked on a similar project for the south runway, milling and paving around 39,000 tonnes of asphalt pavement.

On the north runway, Lafarge Canada is working in collaboration with Kiewit for a full asphalt overlay of the runway and connecting taxiways, with construction scheduled to begin in the this spring and ending in the autumn. Work is planned to coincide with night time runway closures from 10pm to 7am in order to minimise disruptions to flights.

YVR operates a dual runway system, with aircraft typically using the south runway for departures and north runway for arrivals. But this has been altered depending on construction activity and requirements.

In preparation for the start of paving, crews set up the airside laydown site, created access roads and conducted environmental testing around the construction site. This required the programme team to work together seamlessly as planned and complete the early works.

Prior to all this, in March, crews undertook a trial exercise. This trial exercise provided teams the opportunity to refine strategies and plans to safely maximise productivity within the limited construction window each night.

Safety and security remain our top priorities. YVR said it continues to conduct training sessions with its team and contract partners. Training includes wildlife protection, how to safely navigate airside areas and YVR’s Foreign Object Debris (FOD) management programme.

Originally opened in 1996, the north runway will receive a series of upgrades to enhance operational resiliency. The deal, estimated at around US$93 million, will upgrade the runway and improve drainage and electrical systems.

Vancouver Airport announced last October that it had chosen Kiewit to deliver paving and construction services. According to the airport administration, the 9941 foot North runway handles around 370 aircraft movements daily during peak times. The runway and connecting taxiways have around 230mm of asphalt overlay. Asphalt trucks will be timed to ensure optimal flow and noise management, meaning trucks will not come all at once or in close sequence, noted the airport administration.

Airport officials also said this month that there are ongoing sessions with Musqueam for Cultural Awareness Training and Chance Find procedures. Musqueam is a First Nation whose traditional territory encompasses the western half of what is now Greater Vancouver, including the airport. The chance finds procedures are essential for respectful  handling of suspected archaeological or culturally sensitive materials that may belong to First Nation groups and have been accidentally unearthed during construction.

Over the summer, crews will focused on the asphalt overlay and working towards finishing the first pass of the runway slated for completion in June.

Crews will be working on other major infrastructure elements, including subdrain work to upgrade and replace elements of the runway water drainage system, which will improve water removal from the runway surface. Crews will also prepare for the raising of the electrical work in and around the runway.

Visit www.yvr.ca/northrunway for more information about the programme.

For more information on companies in this article

Related Content

  • Asphalt airport runway refurbishment
    February 17, 2012
    Swedish contractor Peab Asfalt generally works on major road and highway projects in the inland portion of the country. However the company has shown itself able to take on a considerable challenge, by repaving an airport runway.
  • Runway resurfacing in Sardinia with Wirtgen machines
    December 7, 2017
    The fleet used comprised two Wirtgen W 210s and one W 200i, as well as two Wirtgen WR 2000 soil stabilisers. Located roughly 8 km north-west of the city of Alghero, Alghero-Fertilia Airport is one of three commercial airports on the Italian island, along with Cagliari Elmas and Olbia. Built as a military airport in the late 1930s, Alghero-Fertilia still occasionally handles military aircraft. However commercial flights represent its main traffic and as it serves the provinces of Sassari and Oristano, it is
  • G&Z paving Canada’s longest runway
    October 12, 2012
    A contractor in Canada, Dufferin Construction, is using three items of new equipment bought from Guntert & Zimmerman to pave the country’s longest runway. The project is extensive, featuring a new runway measuring 4.3km long by 60m wide, an apron area measuring 145,000m2 and two taxiways, each 3.8km long by 25m wide. In all, the work requires 1.5 million tonnes of base aggregate, and 200,000m2 of cement-stabilised base. Dufferin Construction Company, a division of Holcim (Canada) already owns two other G&Z
  • Airport repaving project using machine control
    April 24, 2023
    Luxembourg Airport, located in Findel, is handling a growing number of passenger as well as cargo flights. However, to meet international standards the airport’s runway, measuring 4,000m long x 60m wide, was in need of complete renovation and repair