Kosovo's highway and bridge construction on target

In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
May 4, 2012 Read time: 2 mins
The bridges for Kosovo's Route 7 Highway are being built along modular lines with standardised 40m pre-cast concrete beams being installed over the top of the piers
In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border.

Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousands of Kosovans to celebrate at an opening ceremony.

The project is being carried out by US/Turkish joint venture partners 4138 Bechtel and 5252 Enka, with construction having commenced in the second quarter of 2010. Funding for the project has come from the Kosovan Government itself and route optimisation work by Bechtel-Enka managed to avoid the need for boring twin tube tunnels to the south east of Pristina.

Instead the main Route 7 highway joins with the M9 dual carriageway to the south west of the city, which was built recently by a local contractor. This modified route reduced construction costs for the Route 7 project considerably, a major factor in Bechtel-Enka winning the contract.

The motorway is scheduled for completion in 2013. A full report on this project will be published in the Jan/Feb issue of World Highways.

For more information on companies in this article

Related Content

  • The world’s longest suspension bridge
    June 24, 2024
    The world’s longest suspension bridge is the 1915 Çanakkale Bridge in Turkey. This engineering marvel links Gelibolu with Lapseki, forming a key section of the 101km highway linking Malkara with Çanakkale. *Article produced in partnership with the General Directorate of Highways (KGM), Ministry of Transport and Infrastructure, Republic of Türkiye.
  • Stonehenge tunnel preferred bidder announced
    May 27, 2022
    The preferred bidder has been announced for the UK’s Stonehenge tunnel.
  • Bertha ends her Alaskan Way voyage in Seattle
    December 21, 2017
    Seattle's State Route 99 viaduct is coming down. David Arminas was on site. Bertha, the world’s largest diameter earth pressure balance tunnel boring machine, with a cutterhead diameter of 17.5m, is no more. Her 2.7km journey underneath the waterfront area of Seattle finished on April 4 and the power went off for the last time on an extraordinary TBM that had finally completed an extraordinary job. “A small sidewalk job would have had more impact on city traffic than we have had,” says Brian Russell a v
  • Tunisia is benefiting from key highway expansion
    November 28, 2012
    Work is underway in Tunisia on the westbound Highway from capital Tunis towards the Algerian border. This 60km link will run from the town of Oued Zarga to Boussalem and the work is being carried out by Italian contractor Todini and local company Soroubat. The bidding process for the 100km highway from Gabes to Medenine is now being opened, while bidding for the 92km road from Medenine to the Libyan border outpost of Ras Jedir opened in October 2012. Bids for the construction of the 61km of peripheral roads