Kosovo's highway and bridge construction on target

In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border. Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousan
May 4, 2012 Read time: 2 mins
The bridges for Kosovo's Route 7 Highway are being built along modular lines with standardised 40m pre-cast concrete beams being installed over the top of the piers
In Kosovo, work is pushing ahead of schedule on the Route 7 highway to link capital Pristina with the Albanian border.

Sections of the 120km highway have been opened, one year ahead of schedule. An official opening of several sections of the highway has been carried out by Kosovan leaders, including Prime Minister Hashim Thaçi, President Atifete Jahjaga, and members of Parliament, along with Albanian Prime Minister Sali Berisha and US representatives Eliot Engel (D- NY) and Gary Peters (D-MI) joined thousands of Kosovans to celebrate at an opening ceremony.

The project is being carried out by US/Turkish joint venture partners 4138 Bechtel and 5252 Enka, with construction having commenced in the second quarter of 2010. Funding for the project has come from the Kosovan Government itself and route optimisation work by Bechtel-Enka managed to avoid the need for boring twin tube tunnels to the south east of Pristina.

Instead the main Route 7 highway joins with the M9 dual carriageway to the south west of the city, which was built recently by a local contractor. This modified route reduced construction costs for the Route 7 project considerably, a major factor in Bechtel-Enka winning the contract.

The motorway is scheduled for completion in 2013. A full report on this project will be published in the Jan/Feb issue of World Highways.

For more information on companies in this article

Related Content

  • Texas highway project awarded
    May 31, 2019
    A joint venture team has been awarded the US$1.7 billion I-635 LBJ East infrastructure project in Dallas, Texas. Fluor Corporation heads the joint venture, which also includes Balfour Beatty Infrastructure. The partners will carry out the contract to design and construct the I-635 LBJ East Project in Dallas for the Texas Department of Transportation (TxDOT). The scope of work includes the widening and full reconstruction of nearly 18km of the I-635 route, which is also known as LBJ Freeway. In addition, th
  • Algerian court gives verdict on East-West motorway corruption case
    May 15, 2015
    A court in the Algerian capital Algiers has sentenced two men to 10 years in jail for their part in a money laundering scheme relating to construction of the East West Motorway.
  • Capital move by Turkish Hitachi dealer
    July 31, 2012
    ENKA Pazarlama, one of the longest-serving distributors of Hitachi Constriction Machinery (Europe)/HCME, has opened a new branch in Turkey's capital city, Ankara. ENKA Pazarlama has been serving the Turkish market with Hitachi excavators, wheel loaders and crawler cranes since 1981. The new 12,000m² development is the latest addition to the Turkish dealer's branch network, which includes a number of regional offices, service centres and sub-dealers. Founded in 1972 ENKA Pazarlama is a sub-division of the la
  • Construction to start on Hungary’s revamped M4 project in 2016
    July 7, 2015
    The Hungarian government has announced that it will restart work on a new section of the M4 dual carriageway between Albertirsa and Ullo in 2016. Hungarian media reported that the government will invest around €192 million and no funding will come from the European Union, of which the country is a member. The two towns are around 25.5km apart, with Albertirsa closest to the capital Budapest at around 60km. The project should be finished some time in 2019, according to Hungarian media. The announcem