Key UK bridge project for A38

A key UK bridge project for the A38 over the HS2 route.
By MJ Woof October 29, 2024 Read time: 2 mins
Xxx A new bridge is being built for the A38 route in the UK due to the H2S rail project


Construction is underway for a new bridge that for the A38 route due to the new HS2 rail link in the UK. The work is being carried out by the Balfour Beatty VINCI joint venture. The partners have begun foundation work for the new bridge that will take HS2 trains under a major A road on the outskirts of Lichfield, Staffordshire.

An expert team of engineers has started work directly underneath the A38 carriageway at Streethay to create the foundations of the Rykneld Street bridge, which are from 20-27m-deep. The complex process involves sinking a total of 88 piles nd to support the weight of the structure.
In preparation for the start of piling Balfour Beatty VINCI and National Highways have successfully built a temporary 320m stretch of the A38, which is now in operation. Once piling has been completed and the bridge deck is installed in late 2025, the realigned section of the road will be moved back to its original position where piling is now taking place – allowing space for the high-speed railway to pass underneath.

At 90.5m in length, HS2’s Rykneld Street bridge is the last of three retaining structures to be built at Streethay and contained within a 455m-long cutting through the ground. The trio of bridges, which also includes the A38 Southbound Slip Overbridge and the Streethay Overbridge, will enable the HS2 line to pass under the A38, its slip lanes and the existing South Staffordshire freight railway.
Around 750,000m3 of earth will be excavated during the process of building the three bridges and reused to form embankments along the HS2 route locally. Zachary Walker, Project Manager for Balfour Beatty VINCI, said: “We’re delivering a series of complex structures that will allow HS2 to pass underneath the A38, its slip lanes and the South Staffordshire freight railway near Lichfield. This exciting engineering project is about to move onto the next phase, as we begin the foundation work on the third and final bridge we’re building along this 455m retained cutting in Streethay.”
David Perry, Senior Project Manager for HS2, said: “Carrying out a complex engineering operation of this scale in close proximity to a live carriageway comes with a unique set of challenges, requiring a multi-stage and collaborative approach from everyone involved. 

A series of phased traffic management measures will continue during the build process and road realignment phase, with HS2 and National Highways working together to keep traffic flowing and to minimise disruption for road users.



 

For more information on companies in this article

Related Content

  • Stockholm’s new bypass
    March 8, 2021
    Tunnels make up 18km of the 21km of the Swedish capital’s E4 Bypass mega-project. It will have taken 15 years from start to opening in 2030, if all goes well
  • Tensar’s Glasstex makes the grade in UK’s Smart Motorway upgrade
    February 27, 2017
    A Stress Absorbing Membrane Interlayer is delivering stronger, safer and more reliable surfaces for the UK’s M3 Smart Motorways project in the southern England.
  • Superlative formwork’s global appeal
    April 25, 2013
    The latest formwork solutions are enabling some tough bridge-building projects to be delivered in South America and Europe, while the world’s largest construction equipment show is seeing the merits of other cutting-edge formwork. Guy Woodford reports. Taking a road and rail link across one of South America’s largest rivers, together with its swamps and floodplain, calls for a new crossing of superlative dimensions. Two 135.5m pylons for the third bridge across the Orinoco River in Venezuela are taking shap
  • New Doha highway under construction
    March 18, 2016
    Construction is now underway on the New Orbital Highway in Doha, Qatar. This project is called The New Orbital Highway contract 2 and is one of the largest projects being delivered through the Qatar’s public work authority Ashghal. The work consists of the design and construction of 47km of highway with a five-lane dual carriageway for light vehicles and two truck lanes in each direction. It also includes six viaducts, 17 bridges and underpasses and a 320m cut-and-cover tunnel. This last is particularly