Key UK bridge project for A38

A key UK bridge project for the A38 over the HS2 route.
By MJ Woof October 29, 2024 Read time: 2 mins
Xxx A new bridge is being built for the A38 route in the UK due to the H2S rail project


Construction is underway for a new bridge that for the A38 route due to the new HS2 rail link in the UK. The work is being carried out by the Balfour Beatty VINCI joint venture. The partners have begun foundation work for the new bridge that will take HS2 trains under a major A road on the outskirts of Lichfield, Staffordshire.

An expert team of engineers has started work directly underneath the A38 carriageway at Streethay to create the foundations of the Rykneld Street bridge, which are from 20-27m-deep. The complex process involves sinking a total of 88 piles nd to support the weight of the structure.
In preparation for the start of piling Balfour Beatty VINCI and National Highways have successfully built a temporary 320m stretch of the A38, which is now in operation. Once piling has been completed and the bridge deck is installed in late 2025, the realigned section of the road will be moved back to its original position where piling is now taking place – allowing space for the high-speed railway to pass underneath.

At 90.5m in length, HS2’s Rykneld Street bridge is the last of three retaining structures to be built at Streethay and contained within a 455m-long cutting through the ground. The trio of bridges, which also includes the A38 Southbound Slip Overbridge and the Streethay Overbridge, will enable the HS2 line to pass under the A38, its slip lanes and the existing South Staffordshire freight railway.
Around 750,000m3 of earth will be excavated during the process of building the three bridges and reused to form embankments along the HS2 route locally. Zachary Walker, Project Manager for Balfour Beatty VINCI, said: “We’re delivering a series of complex structures that will allow HS2 to pass underneath the A38, its slip lanes and the South Staffordshire freight railway near Lichfield. This exciting engineering project is about to move onto the next phase, as we begin the foundation work on the third and final bridge we’re building along this 455m retained cutting in Streethay.”
David Perry, Senior Project Manager for HS2, said: “Carrying out a complex engineering operation of this scale in close proximity to a live carriageway comes with a unique set of challenges, requiring a multi-stage and collaborative approach from everyone involved. 

A series of phased traffic management measures will continue during the build process and road realignment phase, with HS2 and National Highways working together to keep traffic flowing and to minimise disruption for road users.



 

For more information on companies in this article

Related Content

  • Velocity-Balfour Beatty tackling potholes
    May 13, 2014
    It is the bugbear of motorists worldwide, and costs UK councils alone an estimated US$82.12 million (£50 million) in compensation each year. Now Balfour Beatty is partnering with specialist supplier Velocity and North Somerset Council in south-west England to tackle potholes using innovative technology which vastly reduces disruption to road users. The method, called ‘Spray Injection’ patching, is allowing Balfour Beatty to repair nearly 700 potholes a week on its highways maintenance contract repairing
  • US$905 million loan for Philippines road
    January 29, 2025
    A US$905 million loan for a Philippines road project
  • Emergent markets key for formwork sector growth
    May 21, 2014
    Central and south-east Europe are hotbeds for new highway infrastructure projects utilising cutting-edge formwork solutions, while a number of leading formwork manufacturers are also looking at emergent markets for growth. Guy Woodford reports Travelling between Hungary’s capital Budapest and Southern Dalmatia now takes less time thanks to the Pan-European Corridor Vc – European route 73. Numerous tunnels and bridges are erected along the 397km stretch of the European route 73 through Bosnia owing to the
  • Balfour Beatty wins road contract for Norfolk
    November 27, 2015
    Balfour Beatty has been awarded a €147.72 million (£104 million) road scheme by Norfolk County Council to complete works on the Norwich Northern Distributor Road (NNDR). The new road will serve Broadland, Norfolk, and improve access to North Norfolk and Norwich International Airport, with better links to Great Yarmouth and the south of the region. It will also bring relief on congested and unsuitable roads around the north and east of Norwich and improve capacity for future growth in jobs and housing.