A key UK bridge project for the A38 over the HS2 route.
By MJ Woof October 29, 2024 Read time: 2 mins
Xxx A new bridge is being built for the A38 route in the UK due to the H2S rail project


Construction is underway for a new bridge that for the A38 route due to the new HS2 rail link in the UK. The work is being carried out by the Balfour Beatty VINCI joint venture. The partners have begun foundation work for the new bridge that will take HS2 trains under a major A road on the outskirts of Lichfield, Staffordshire.

An expert team of engineers has started work directly underneath the A38 carriageway at Streethay to create the foundations of the Rykneld Street bridge, which are from 20-27m-deep. The complex process involves sinking a total of 88 piles nd to support the weight of the structure.
In preparation for the start of piling Balfour Beatty VINCI and National Highways have successfully built a temporary 320m stretch of the A38, which is now in operation. Once piling has been completed and the bridge deck is installed in late 2025, the realigned section of the road will be moved back to its original position where piling is now taking place – allowing space for the high-speed railway to pass underneath.

At 90.5m in length, HS2’s Rykneld Street bridge is the last of three retaining structures to be built at Streethay and contained within a 455m-long cutting through the ground. The trio of bridges, which also includes the A38 Southbound Slip Overbridge and the Streethay Overbridge, will enable the HS2 line to pass under the A38, its slip lanes and the existing South Staffordshire freight railway.
Around 750,000m3 of earth will be excavated during the process of building the three bridges and reused to form embankments along the HS2 route locally. Zachary Walker, Project Manager for Balfour Beatty VINCI, said: “We’re delivering a series of complex structures that will allow HS2 to pass underneath the A38, its slip lanes and the South Staffordshire freight railway near Lichfield. This exciting engineering project is about to move onto the next phase, as we begin the foundation work on the third and final bridge we’re building along this 455m retained cutting in Streethay.”
David Perry, Senior Project Manager for HS2, said: “Carrying out a complex engineering operation of this scale in close proximity to a live carriageway comes with a unique set of challenges, requiring a multi-stage and collaborative approach from everyone involved. 

A series of phased traffic management measures will continue during the build process and road realignment phase, with HS2 and National Highways working together to keep traffic flowing and to minimise disruption for road users.



 

For more information on companies in this article

Related Content

  • Staffordshire road improvements planned
    July 29, 2024
    Staffordshire road improvements will commence shortly.
  • Clever electric solution for embankment stabilisation
    August 28, 2013
    A highly innovative solution for road embankment stabilisation has helped save costs by up to 30% over conventional techniques. Balfour Beatty Mott MacDonald has used electrical current to stabilise embankments on a busy UK dual carriageway, avoiding disruption to motorists, cutting carbon by 40% and costs by 30%, and producing zero waste When slope failure was detected on embankments carrying the popular A21 dual carriageway, Balfour Beatty Mott MacDonald pioneered a novel technique to tackle the prob
  • Mini-bridge aids Forth repairs
    July 17, 2012
    An engineering "first" means that rehabilitation work on a vital Scottish bridge built over 40 years ago can be carried out smoothly A new report to the Forth Estuary Transport Authority (FETA) in Scotland recommends appointing Balfour Beatty Civil Engineering of Edinburgh as 'preferred bidder' to carry out the scheduled replacement of the bridge's main expansion joints in 2009. However, the report to the bridge authority says the tender price of £13.7 million (US$21.3 million) is some £5 million ($7.8 mill
  • Widening for key section of UK’s A11 route complete
    December 12, 2014
    Contractor Balfour Beatty has completed the €132.4 million (£105 million) upgrade of the last remaining single carriageway section of the A11. This section of the route runs between Barton Mills in Suffolk and Thetford in Norfolk. The work involved dualling nearly 15km of carriageway on behalf of the Highways Agency.