Izmir, Turkey motorway project set to be delayed by at least 18 months

The construction of the Istanbul-Izmir motorway in Turkey is set to be delayed by at least 18 months due to insufficient funds being in place to complete the major new highway. Turkey's Transport and Communication Minister Binali Yildirim has warned the Nurol-Özaltn-Makyol-Astaldi-Yüksel-Göçay joint venture, who are responsible for the construction of the motorway, that it will be in breach of the project’s contract, signed in October 2010, imposing a strict completion deadline of five-and-a-half years.
December 20, 2012 Read time: 1 min
The construction of the Istanbul-Izmir motorway in Turkey is set to be delayed by at least 18 months due to insufficient funds being in place to complete the major new highway.

Turkey's Transport and Communication Minister Binali Yildirim has warned the 3338 Nurol-Özaltin-3340 Makyol-1324 Astaldi-4149 Yüksel-3342 Göçay joint venture, who are responsible for the construction of the motorway, that it will be in breach of the project’s contract, signed in October 2010, imposing a strict completion deadline of five-and-a-half years.

So far, US$500 million (€382.34mn) has been spent from the equity capital for the Istanbul-Izmir motorway works.

For more information on companies in this article

Related Content

  • UK smart motorway work for M4 link
    September 16, 2019
    Highways England in the UK is carrying out major upgrade work for the busy M4 motorway, running west from capital London. In all 11 bridges are being replaced along a 51km stretch of the M4 between London and Reading. When complete, the current hard shoulder will have been rebuilt and resurfaced to allow traffic to use it as a live lane. The section carrying the heaviest traffic, between the M25 ring road around London and the main exit for Heathrow Airport, will be widened so that it will feature five la
  • Asphalt resurfacing at Miami International Airport
    February 8, 2012
    Improvements worth US$30 million are being carried out at Miami International Airport. The work includes runway resurfacing with specialist contractors having been brought in to handle the project. This is a busy facility handling some 34 million passengers/year and the work is being carried out over a period of 454 days in all, starting in September 2009 and due to finish in December 2010. The focus of attention is the upgrade to the airport's second longest runway, 8R 26L as well as the adjoining M and N
  • Road maintenance crisis hits UK and US, as experts gather in Paris
    January 9, 2015
    The road maintenance crisis in the United Kingdom and the United States is deepening amid estimates that it will take millions of dollars to stop highway infrastructure from crumbling, including falling prey to potholes. A recent report by the BBC in the UK said that at least one municipal council, the city of Leeds, is facing a bill of nearly US$153 million to patch up its potholed roads. In the United States, Senator Bernie Sanders is t
  • $627 million road tolling plan for Raleigh
    May 15, 2025
    A $627 million road tolling plan for Raleigh’s Capital Boulevard.