Two key highway projects in Italy are exhibiting good progress at present. Construction work on the new Brescia-Milan highway link is now more than 50% complete. The bridges crossing the Serio, Adda and Oglio rivers are 84% complete, while the underpasses and drainage is 49% ready. Service stations, surveying and foundation work is 40% complete while the remaining operations are progressing. Italian road construction firm Brebemi believes that the highway be will be complete and open to traffic by 31 Decemb
December 17, 2012 Read time: 2 mins
Two key highway projects in Italy are exhibiting good progress at present. Construction work on the new Brescia-Milan highway link is now more than 50% complete.

The bridges crossing the Serio, Adda and Oglio rivers are 84% complete, while the underpasses and drainage is 49% ready. Service stations, surveying and foundation work is 40% complete while the remaining operations are progressing. Italian road construction firm Brebemi believes that the highway be will be complete and open to traffic by 31 December 2012. The €2.4 billion financing agreement is being provided by a group of banks is expected to be finalised by November 2012. Meanwhile a loan from the 1054 European Investment Bank (EIB) worth €500 million has been granted to Italian highway operator  3623 Autostrade per l'Italia (ASPI). The first €250 million tranche of the loan will be used to develop the A1 tolled highway running from Florence-Bologna. The sum will be used for work on the Firenze Nord - Barberino del Mugello stretch of the highway. The A1 is one of Italy's main highways, forming part of the Transeuropean Transport Networks (TENs) Corridor 1.

For more information on companies in this article

Related Content

  • Second Danube bridge construction approved
    May 15, 2012
    Official approval is now being given for changes to the agreement between the Bulgarian authorities and the European Investment Bank (EIB) for the second Danube bridge project. So far the EIB is providing €50 million, with €5 million having already been used. The Bulgarian authorities are agreeing to accept a shorter loan period of 14.5 years rather than the 17-year term originally agreed with the EIB.
  • India pushing ahead with infrastructure projects
    July 4, 2012
    Despite the economic downturn, India looks to be pressing ahead with its major infrastructure projects to further boost its incredible growth. Patrick Smith reports India, which like most countries has been affected by the current economic climate, although not to the same extent, is pressing ahead with its ambitious highway construction plans. Each week new projects are completed, started or awarded as the nation seeks to improve its transportation requirements. These are needed to meet the aspirations of
  • Progress delayed on Kenya's vital highway link
    February 16, 2012
    Kenya is investing in road developments , reports Shem Oirere. A multi-million dollar highway expansion project in Kenya's capital Nairobi may now be delayed for close to a year because of a huge underground network of water, electricity and communication pipes and cables that has slowed down construction works.
  • Bosnia agrees funding for highway construction plans
    March 22, 2012
    Bosnia’s highway company Autoceste Federacije BiH will invest €500 million in the construction of the Corridor Vc road. The European Investment Bank (EIB) will provide a loan of €166 million to part finance the project. The plans call for the construction of the 56km highway as well as an additional 10km of the Sarajevo ringroad. The cost of the project is three times higher than any other that the country has so far planned. Autoceste Federacije BiH has said that it will finance land expropriation.