Ireland's budgert cuts impact on road projects

Ireland’s government is undergoing a period of belt-tightening, with a string of budget cuts that will directly impact on the transport sector. The country was in the process of spending heavily on its infrastructure but with the tough economic climate it is now facing, a number of road projects are among those facing the axe. The Irish government is slashing its infrastructure spending from €39.6 billion to €22.9 billion between now and 2013. This looks likely to result in 40 road projects, including hig
May 14, 2012 Read time: 2 mins
RSSIreland’s government is undergoing a period of belt-tightening, with a string of budget cuts that will directly impact on the transport sector.

The country was in the process of spending heavily on its infrastructure but with the tough economic climate it is now facing, a number of road projects are among those facing the axe.

The Irish government is slashing its infrastructure spending from €39.6 billion to €22.9 billion between now and 2013. This looks likely to result in 40 road projects, including highways and dual carriageways, being shelved or cancelled.

Ireland’s 5525 National Roads Authority (NRA) has been told not to build previously planned rest areas along highways, with the
Atlantic Corridor Road linking Letterkenny and Waterford one of only a few projects that will remain in hand.
However, the NRA is planning the M20 motorway that will link the cities of Limerick and Cork.

Planning permission is being sought at present for the 80km road, which will be built in two phases: the first stage will run for around 40km from Kileens to Velvetstown while the second phase runs from Buttevant to Attyfield.

The project is expected to cost €800 million and the NRA hopes to begin construction of the first phase of the road in 2012, assuming that approval and funding can be secured.

Work on the second stage would start after the completion of the first phase in 2015, with the project planned for a completion date in 2018. However, with Ireland’s slow down on its infrastructure investment at present following the financial crisis it is not clear if the M20 project will be delayed.

For more information on companies in this article

Related Content

  • Serbia’s pan-European Corridor X is in the slow lane
    October 23, 2017
    It’s been slow progress on Serbia’s Corridor X project. Gordon Feller reports. Back in the early 2000’s, the European Union undertook an ambitious programme to link the main cities of its south-eastern region. This involved connecting five key seaports – the Greek cities of Patras, Igoumenitsa, Piraeus and Thessaloniki as well as Romania’s Black Sea city of Constanta. Initially the plan involved two motorways across Greece. The first was a new 780km route including a branch to Ormenio on Greece’s north-eas
  • Ireland boosts road and transport budget
    July 4, 2017
    The Irish Government is boosting its budget for transport spending by a further €1 billion.
  • Design contract for Irish motorway
    March 19, 2019
    The design contract for Ireland’s Cork to Limerick motorway connection has now been awarded. The design package is worth €15 million and is being handled jointly by Irish firm JB Barry Transportation, Swedish company Sweco and WSP based in Canada. Building the 100km stretch of the M20 motorway is expected to cost €900 million, including eight major bridges over rivers, 44 smaller bridges over roads and two bridges over rail links. The work would also include building some small river crossings as well as up
  • Poland's ambitious highway construction plans
    July 10, 2012
    The European football championships are among a number of things pushing Poland's ambitious highway building programme. Patrick Smith reports. Poland is planning to spend a colossal €4.57 billion on road projects in 2009, a 35% increase over the previous year. T