The installation is underway of the first superspan gantries on the M4/M5 managed motorway scheme. The existing gantries and infrastructure were successfully removed last month while the new steel gantries were being constructed, fitted-out and tested at a dedicated facility located near junction 17 of the M5, before being delivered to the works site. A total of 33 new overhead gantries, a number of which span 50m and weigh over 30tonnes, will be installed along the new managed motorway section up until T
July 4, 2012 Read time: 3 mins
One of the superspan gantries being fitted for the M4/M5 managed motorway scheme
The installation is underway of the first superspan gantries on the M4/M5 managed motorway scheme.

The existing gantries and infrastructure were successfully removed last month while the new steel gantries were being constructed, fitted-out and tested at a dedicated facility located near junction 17 of the M5, before being delivered to the works site.

A total of 33 new overhead gantries, a number of which span 50m and weigh over 30tonnes, will be installed along the new managed motorway section up until Thursday 12 July. A further seven existing gantries are being upgraded to take new signage. Information displayed on the gantries will advise drivers when the hard shoulder is open for use by traffic, display variable speed limits to manage traffic flow and reduce congestion, and also provide information on the road conditions.

To enable installation of the overhead gantries, there will be a series of week-night closures throughout July. The first set of 10pm to 6am closures began on Tuesday 3 July and will finish Thursday 5 July on the M4 and M5 carriageways. Clearly signposted diversion routes will be in place throughout the works which affect:

  • Tuesday 3 July: M4 Eastbound and Westbound through junction 20

  • Wednesday 4 July: M5 Northbound junction16 to 15 and M5 Southbound junction 14-16

  • Thursday 5 July: M5 Northbound junction 17-15 and M5 Southbound junction 15-16

There will also be further week-night link road closures from Monday 9 July to Thursday 12 July, from 9pm until 6am the following morning at:

  • Monday 9 July: M5 South to M4 East link road and M5 South to M4 West link road

  • Tuesday 10 July - Thursday 12July: M5 South to M4 East and West link roads and M4     East to M5 North and South link roads

Paul Unwin, 2309 Highways Agency senior project manager, said: “The new gantries will hold the signs and signals that will convey vital road information to drivers. Their sheer size means that a full motorway closure is essential to give us access for delivery and installation.

“Closing the motorway also ensures the safety of the travelling public as road workers with large and heavy equipment complete the task of installing the gantries and associated technology.”

Unwin said that although the closures would be in place at times of less traffic, road users are being encouraged to allow more time for their journeys and to follow the signed diversion routes.

The work is part of delivering the managed motorway scheme which will introduce variable mandatory speed limits and allow the hard shoulder to be used as an extra traffic lane on the M4 between junctions 19 and 20, and the M5 between Junction 15 and Junction 17, during heavy traffic flow.

Mobilisation work for the M4/M5 managed motorway scheme started on 7 November, 2011. Main construction work started in January 2012, with work due to be completed in spring 2014.

For more information on companies in this article

Related Content

  • Smart motorway project for UK’s M3
    July 23, 2014
    Balfour Beatty is to work on a €163.5 million (£129 million) upgrade project for a 21.4km stretch of the M3 motorway in the UK. The work involves upgrading the route to smart motorway status and is being carried out for the UK Government’s Highways Agency. This project will increase capacity, reduce congestion and shorten journey times for the 120,000 motorists/day using the route. This section of the motorway runs through the counties of Hampshire and Surrey, between Junction 2 which is interchange with th
  • Skanska Balfour Beatty install first M25 superspan gantry during motorway upgrade
    August 22, 2013
    The first superspan gantry has been installed over the M25 motorway near London, England. The structure near Junction 24 (Potters Bar, Hertfordshire) is part of the €219.92 million (£188 million) Managed Motorway scheme to upgrade the motorway between junctions 23 and 27. Weighing 36 tonnes and measuring 40m across, it is the first of five superspan gantries which will be installed during the project being carried out by Skanska Balfour Beatty, on behalf of the Highways Agency. The gantries will
  • Completion due shortly for UK’s A30 project
    February 11, 2025
    Completion of the UK’s A30 upgrade project is due shortly.
  • New UK dual carriageway opening
    December 20, 2016
    Drivers in the UK are to benefit from the opening of a new dual carriageway connection. The section of road is a key route for Highways England, improving the connection between junction 19 of the M6 and junction 7 of the M56 motorways. The new A556 Knutsford to Bowdon link road will cut congestion and journey times for drivers in the area. As part of the £192 million project to build the new dual carriageway between, Highways England has remodelled slip roads at Yarwood Heath and Bowdon roundabouts. The