Indeco reveals new system for selecting tunnelling methods

Italian hydraulic breaker manufacturer Indeco is introducing a new approach to selecting tunnelling methods. The firm says that this has been developed in response to a tunnelling industry that is too-ready to select tunnel boring machines (TBMs).
January 6, 2017 Read time: 2 mins
Indeco: new approach
Italian hydraulic breaker manufacturer Indeco is introducing a new approach to selecting tunnelling methods.

The firm says that this has been developed in response to a tunnelling industry that is too-ready to select tunnel boring machines (TBMs). 237 Indeco’s marketing and commercial manager, Michele Vitulano explained that TBMs are highly efficient in the right conditions and have achieved major successes in a number of projects. However, he said also that these machines are also hampered by a lack of versatility. Changes in rock conditions can cause serious problems such as excessive cutter wear or even breakdowns.

Mauro Amato, product and project manager at Indeco explained that the firm has developed an Analytical Hierarchy Process (AHP) that provides a simplified process for selecting the best excavation method for a tunnelling project.

In Italy tunnelling projects are often carried out using hydraulic breakers fitted to excavators, with loading and hauling equipment to carry away the waste materials. Vitulano asked, “Why are Italian companies working like that?”

And he explained that the complex geology of Italy has meant that for many tunnelling projects, the conditions are not sufficiently homogenous to allow the use of TBMs. Hydraulic breakers have been well proven in tunnelling applications in Italy, as they suit the often fractured or faulted rock conditions. This equipment is comparatively inexpensive, as well as being reliable and versatile. A TBM by comparison is highly expensive to purchase and also requires considerable logistics to supply and install on site.

When fitted to an excavator, a hydraulic breaker provides a highly versatile method. It can be used as a back up to a TBM for difficult tunnelling conditions, as well as playing a similar role with drilling and blasting methods. Alessandro Ciccolella is research and development manager at Indeco and said, “Using a breaker, a contractor can follow fault lines of the rock and increase productivity. It is a precision tool that allows selective excavation.”

He added, “There is a risk factor with a TBM that is totally overlooked by the tunnelling industry. Blasting and breaking are not methods of the past for tunnelling. That’s what we want to highlight.”

For more information on companies in this article

Related Content

  • MB Crusher: Pushing attachment boundaries since 2001
    June 15, 2023
    For over 20 years, MB Crusher has offered a full line of innovative and patented jaw crusher and screener buckets and accessories for excavators, skid-steer loaders and backhoes of all sizes. Guy Woodford sat down with Alessia Valerio, MB's communications manager, at the recent 31st edition of SaMoTer in Verona to learn more about the company's latest developments and future growth plans
  • Key Chinese tunnel project going ahead
    August 14, 2020
    Work is going ahead for a key Chinese tunnel project.
  • HxGN Live 2014 attracts record event numbers
    August 28, 2014
    Attracting an HxGN Live event record-breaking 3,500 attendees, HxGN Live 2014 held at the MGM Grand in Las Vegas, US, June 2-5 showcased exciting new and in-demand design, measurement and visualisation technologies for industries including road construction and mining. Themed Great Stories Start Here, this year’s event also included a variety of exclusive presentations by industry experts, hands-on training, inspiring keynotes and international networking opportunities. Guy Woodford reports In
  • Building the diamond road in Lesotho
    April 6, 2016
    A job site in the Southern African nation of Lesotho represents one of the most extreme and challenging projects to some key Italian firms of the last 10 years. The project was certainly different from the norm It involves building a road in the Lesotho Mountains, some 200km from the capital Maseru, with the work being carried out by the Cooperative of Building and Cement workers from Ravenna (CMC). CMC, which has ranked among Marini's clients for many years now, is involved in the construction of a