Healthy bidding for Poland's highway construction

Bidding is healthy for a section of dual carriageway in Poland linking Kurow with Lublin. The section is 60km long and has been divided by the Polish General Directorate for National Roads and Motorways (GDDKiA) into five separate bids.
May 14, 2012 Read time: 2 mins
Bidding is healthy for a section of dual carriageway in Poland linking Kurow with Lublin.

The section is 60km long and has been divided by the 3519 Polish General Directorate for National Roads and Motorways (GDDKiA) into five separate bids.

The completion of the tenders is scheduled for May 2010. Meanwhile the authorities in the city of Lublin are opening up the tender process for a road to connect with the city’s ring-road. The project is expected to cost over €52 million. Only up to seven investors will be allowed to take part in the tender.

3302 Budimex 3546 Dromex is starting construction work for the 33km section of Poland’s A4 highway between Debica Pustynia and Rzeszow. The deal is worth nearly €435 million and the contractor, a subsidiary of Polish construction firm Budimex, won the tender with the lowest offer for the work.

Meanwhile contractor 1547 NDI has put in the lowest tender for the 34km section of the A4 between Krzyz and the Debica Pustynia junction. NDI has put in a bid of €251 million while the highest bid for the work was nearly €337 million.

A €200 million loan from the 1054 European Investment Bank (EIB) will provide partial funding for Poland’s highway improvement programme. This loan will be used for upgrading an 8km stretch of the A6 highway between Klucz and Kijewo. The loan will also provide partial funding for construction of a 57km section of the A1 highway between Gorzyczki, Sosnica and Maciejow, as well as a 51km stretch of the A4 highway between Zgorzelec and Krzyzowa. Poland’s highway network has already benefited from EIB loans worth €300 million.

Related Content

  • Delays on Slovakian projects
    July 9, 2012
    Work on several new highways being built in Slovakia as public-private partnerships (PPPs) will be delayed by six to 12 months. This means that the first sections of the Martin-Presov link will not open before 2011. The last section is expected to be completed in either late 2012 or early 2013.
  • Poland tenders for more A2 work between Lodz and Warsaw
    January 8, 2019
    A tender has been announced to build a third lane for the A2 motorway between Lodz and Warsaw in Poland. According to the Polish General Directorate for National Roads and Motorways (GDDKiA), the cost will be around €139 million with completion set for 2021. The A2 is part of the country’s road infrastructure connecting Poland with the European motorway network. The A2 Motorway is part of the TransEuropean Road Network (E30) from Cork in Ireland to Omsk in Russia and is located in Pan-European transport
  • Astaldi wins contract for part of Romania’s Brasov–Oradea motorway
    April 19, 2016
    Italian contractor Astaldi, as part of a joint venture, has won a €100 million contract to build of motorway in Romania. The contract is 18km of the Brasov–Oradea section of the partially built A3 Autostrade, a 584km route that runs north to south, from the border with Hungary to the capital Bucharest. Astalsi’s design and construction work includes three viaducts, five overpasses, three flyovers, and one motorway interchange. Work will begin in May and last for 16 months. Work on the Brasov-Oradea
  • Slovakia’s troubled D1 highway
    February 20, 2012
    Slovakia’s Ministry of Transport is to finance construction work on the 75km section of D1 highway between Martin and Presov from state funds, with work expected to start in the second quarter of 2011.