Skip to main content

Go-ahead for controversial highway

APPROVAL HAS now been given for work to go ahead on a key section of Slovakia’s D1 highway. The work had been delayed as the European Commission (EC) was concerned over environmental issues facing sections of the route that passed through a nature reserve. The EC has now given its approval for construction of the highway between Martin and Presov on conditional terms. The EC says that the sections in zones belonging to the Natura 2000 network can be built once terms are agreed with the Slovak government o
May 30, 2012 Read time: 2 mins
APPROVAL HAS now been given for work to go ahead on a key section of Slovakia’s D1 highway.

The work had been delayed as the 2465 European Commission (EC) was concerned over environmental issues facing sections of the  route that passed through a nature reserve. The EC has now given its approval for construction of the highway between Martin and Presov on conditional terms.

The EC says that the sections in zones belonging to the Natura 2000 network can be  built once terms are agreed with the Slovak government on compensations for environmental damage. This decision means that construction works can now start between Poprad and Presov and most parts of the Martin-Ruzomberok section. The approval allows the 1054 European Investment Bank (EIB) to provide a €1 billion loan for the project.

The highway will be built by the consortium  of 2877 Doprastav and Vahostav as a public-private partnership (PPP) under a 30-year concession deal.

The eastern part of the 75km road is expected to open in 2012 and the Martin-Ruzomberok section in 2013.

Although the EIB approved the whole loan, the EC approval is only for certain sections and any works affecting zones which are part of the Natura 2000 network must be postponed until the EC says that the project complies with EU  regulations. The controversial sections include a peatland close to the Natura 2000 zone and pillars in the Vah River which could affect the local environment.

The 2875 Slovakia’s Ministry of Transport says that  99% of problems related to the Turany-Hubovy section have been already resolved, although Priatelia Zeme-CEPA, the Slovak branch of the  Friends of the Earth, and other environmentalist groups claim that construction of the D1  motorway in the Turany-Hubova section cannot comply with the EU Biotop Protection Directive.

Related Content

  • Hungarian highway getting underway
    April 25, 2012
    Work to construct a new stretch of Hungary’s M43 highway, linking Mako and Csanadpalota/Nagylak on the Romanian border, is costing some €212 million. The cost of the work is being split 39% and 61% by Hungarian state funds and EU funding respectively. Construction work on the 23km long section will be completed by the end of 2014. The project has to be approved by the European Commission (EC), as it will form part of the trans-European transport network (TEN-T). Plans are to be submitted to the EU by the Hu
  • Black sea countries complete preparations for implementation of Black Sea Ring project
    August 23, 2016
    The Black Sea Ring Road project will improve transport connections for the region - Eugene Gerden writes. Russia has officially started implementation of a project, known as the Black Sea Ring Road, which involves building a four-lane highway system connecting the countries surrounding the Black Sea. The Black Sea Ring Road is a substantial project, a highway measuring some 7,140km in all. Among the countries participating in the project are Turkey, Georgia, Russia, Ukraine, Moldova, Romania, Greece and
  • Bosnia agrees funding for highway construction plans
    March 22, 2012
    Bosnia’s highway company Autoceste Federacije BiH will invest €500 million in the construction of the Corridor Vc road. The European Investment Bank (EIB) will provide a loan of €166 million to part finance the project. The plans call for the construction of the 56km highway as well as an additional 10km of the Sarajevo ringroad. The cost of the project is three times higher than any other that the country has so far planned. Autoceste Federacije BiH has said that it will finance land expropriation.
  • ECED construction machinery dealers think tank
    July 4, 2012
    ECED's first 'Machinery Dealers Think Tank' in Lisbon proved a big success Dr. José Gameiro, President of the European Confederation of Equipment Distributors (ECED) and a member of the Board of the Portuguese association ACAP, hosted the Fall General Assembly of the ECED Lisbon, Portugal. Preceding this bi-annual formal gathering (on 22 November), Dr. José Gameiro welcomed 17 independent distributors from Portugal, France, UK, Spain, Austria and Eastern Europe, as well as seven of the most prominent nation