German court decides for Fehmarnbelt

Danish state-owned company Femern is responsible for the 18km road-rail tunnel.
By David Arminas November 18, 2020 Read time: 1 min
Work continues in June on a breakwater for the harbour in Rødbyhavn where sections of the tunnel will be constructed and floated out for placement (photo copyright Femern/Nils Lund Pedersen)

Germany’s federal administrative court has decided that the planned Fehmarnbelt Tunnel between the Danish island of Lolland and the German island of Fehmarn can proceed.

The case to delay construction began at the end of September. Six of the nine complaints were recently dismissed unconditionally while three complaints were settled out of court, according to the German newspaper Suddeutsche Zeitung.

The Danish state-owned company Femern is financing, building and will operate the approximately 18km road and rail tunnel under the Baltic Sea at a cost around €7.5 billion to construct. The tunnel, expected to open in 2029, should reduce the passenger train time from Hamburg in northern Germany to the Danish capital Copenhagen by around two hours, making the journey around two and a half hours.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps and portals). Meanwhile, SWECO is handling the design for the dredging and reclamation work.

For more information on companies in this article

Related Content

  • Hamburg highway expansion programme
    May 20, 2015
    A €1.6 billion project is in hand in Germany to widen the A7 Autobahn between Bordesholm and Hamburg's tunnel Elbtunnel. Funding for the project is being provided jointly by the German Government, the city of Hamburg, the province of Schleswig-Holstein and the German engineering firm Deutsche Einheit Fernstraßenplanungs- und -bau (DEGES). The work should be complete by 2018. The project involves increasing the number of traffic lanes in the Schleswig-Holstein section from four to six and in Hamburg from six
  • Romania to start work on the Sibiu-Pitesti A1 section in 2017
    April 17, 2015
    Work will start on the 120km Sibiu-Pitesti section of Romania’s A1 Freeway in 2017, Romanian media report. Around €1.6 billion will be spent on the route that will run through 20km of mountains. In February, the National Highway and Roads Company, CNADNR, selected the Milan-based Spea Ingineria Europea and Tecnic Consulting Engineering of Romania to update the feasibility study on the section, which is part of Romania’s A1 Freeway. But that contract has been challenged and will be scrutinised by th
  • Lueg Bridge work sparks congestion fears
    June 23, 2022
    Lueg Bridge, along Austria’s section of the Brenner Pass route, is slated for major rehabilitation work as part of upgrades to the tolled motorway.
  • Canada, US officials soon to settle planned Detroit bridge issue
    February 5, 2015
    An end to a thorny issue is close at hand concerning who will fund construction of a border customs plaza on the US side of a planned bridge linking Canada and the United States. US President Barack Obama’s US$4-trillion budget did not set aside any money for the plaza for a second consecutive year, further irritating Canadian officials who are overseeing construction of the bridge. It appears that the Canadian government might end up footing the entire bill, according to a report in Toronto’s Globe a