German court decides for Fehmarnbelt

Danish state-owned company Femern is responsible for the 18km road-rail tunnel.
By David Arminas November 18, 2020 Read time: 1 min
Work continues in June on a breakwater for the harbour in Rødbyhavn where sections of the tunnel will be constructed and floated out for placement (photo copyright Femern/Nils Lund Pedersen)

Germany’s federal administrative court has decided that the planned Fehmarnbelt Tunnel between the Danish island of Lolland and the German island of Fehmarn can proceed.

The case to delay construction began at the end of September. Six of the nine complaints were recently dismissed unconditionally while three complaints were settled out of court, according to the German newspaper Suddeutsche Zeitung.

The Danish state-owned company Femern is financing, building and will operate the approximately 18km road and rail tunnel under the Baltic Sea at a cost around €7.5 billion to construct. The tunnel, expected to open in 2029, should reduce the passenger train time from Hamburg in northern Germany to the Danish capital Copenhagen by around two hours, making the journey around two and a half hours.

A Rambøll-Arup-TEC consultancy joint venture is engaged in a client consultancy services contract with Femern. The joint venture has also worked on other landmark infrastructure projects, including the Øresund Tunnel in Denmark, the City Tunnel in Malmö, Sweden, the Medway Tunnel in England, as well as underground rail systems in Amsterdam and Copenhagen.

COWI is carrying out the detailed design of the tunnel (north tunnel section, south tunnel section, and ramps and portals). Meanwhile, SWECO is handling the design for the dredging and reclamation work.

For more information on companies in this article

Related Content

  • New Zealand’s Waterview project is moving closer to completion
    December 13, 2016
    New Zealand’s biggest road project is less than a year away from completion, and a lot of progress has been made since World Highways last looked at the project two years ago - Mary Searle Bell reports New Zealand’s Waterview project is moving closer to completion and will be the largest road project in the country. The NZ$2 billion Western Ring Route will see the creation of an alternative motorway to State Highway 1, which runs through the centre of Auckland. The 47km-long motorway will allow a large p
  • Amey and Arup win UK contract to upgrade A66
    May 27, 2020
    Amey Consulting and Arup have won a UK contract to upgrade the A66 route.
  • GRAA focuses on winning project profile: Brisbane Airport Link, Northern Busway & Airport
    May 19, 2014
    The revolutionary AUD$4.8 billion Airport Link has delivered a landmark infrastructure project for Australia, tackling traffic congestion, enhancing the busway network and removing an infamous traffic bottleneck through an innovative and inspired design. The Airport Link in Brisbane, Australia included three separate projects – the Northern Busway (a 3km two-way dedicated busway), the Airport Roundabout Upgrade and the AirportlinkM7 (a 6.7km toll road including 5.2km of tunnel). Together, they represent the
  • Aarhus stops some road works over price hikes
    June 1, 2022
    The Danish city of Aarhus says it is shutting down some roadworks as prices rise for aggregates.