Genoa bridge becoming symbol of Italy’s resurgence during pandemic

Another milestone for PerGenova with simultaneous installation of two deck sections.
By David Arminas April 10, 2020 Read time: 3 mins
Another bridge deck section is carefully lifted into place for the Genoa bridge replacement project (photo courtesy PerGenoa)

Despite the Covid-19 lockdown in Italy – one of the world’s hardest hit nations – work on the Genoa bridge continues, with more deck sections in position.

Another milestone has been reached with the simultaneous installation of two deck sections to bring to more than 900m the structure’s installed length, according to PerGenova, the joint venture in charge of the project.

Thanks to the recently implemented fast-track model that has seen various activities proceed simultaneously throughout the construction site, a section of the deck, 51m long and weighing 410 tonnes, was raised 40m up between Piers 12 and 13 on the east side of the riverbed.

Also, a 15m, 114 tonne section of Abutment A was hoisted between Piers 1 and 2 on the west side with the help of a temporary tower.

PerGenova JV – Salini Impregilo and Fincantieri – is also proceeding with work on the already-installed part of the structure and preparing to raise the last four sections of the deck to complete the bridge. Technicians and workers are maintaining a high production rate while respecting the safety measures in order to complete the structure with all the sections of the deck installed by the end of April, says the JV.

“It is the success of a marvellous, cohesive team,” said Nicola Meistro, general manager domestic operations at Salini Impregilo and chief executive of PerGenova.

“All of our people have shown a great ability to adapt to this new context. It is thanks to them and the suppliers and the rest of the production chain that work alongside us every day in full respect of the rules, that the Genoa Bridge is a model for Phase 2 for all of Italy, a country of people who in times of difficulty know how to roll up their sleeves in a show of confidence and courage.”

The construction site of the new bridge is deploying extraordinary measures as a result of the coronavirus. These include measuring the body temperature of every worker who enters the site, distributing hand sanitisers and installing disinfectant gel dispensers, enforcing the safe distance rule, cleaning and disinfecting work sites and common areas and reducing the number of people who travel in the same vehicle to and from the site.

In addition, all workers have protection masks whose use is obligatory when they are close to their colleagues. These measures are but a summary of what has been adopted at the site, much like those at sites elsewhere in the world operated by the Salini Impregilo Group as it confronts the health emergency with a task force that is operating at a global level.

Work proceeds on the access ramp of the highway as well as the complex operation to prepare the base of the installed deck. Around 8,000m³ of concrete will be poured, starting at both ends of the bridge at the same time and working  towards the centre. This activity will be done round the clock.

“We are giving it everything we’ve got and speeding up the work as much as possible,” said Francesco Poma, senior project manager for Italy with Salini Impregilo and project manager of the bridge work.

The bridge is illuminated every evening with three lasers beaming the colours of the Italian flag to create a Bridge of Light to express Salini Impregilo’s solidarity with the country and transmit to Genoa a message of hope for the future.

Related Content

  • Australian bridge slides into position
    July 18, 2012
    A heavy rail crossing as part of Australia's EastLink motorway demanded great ingenuity and careful planning Most of the 88 bridges on the EastLink tolled motorway in, Melbourne, Australia were kept as simple and straightforward as possible. Contractor Thiess John Holland (TJH) developed its own precast yard 150km from the city, which provided many of the prefabricated materials required for the structures. This offered speed and economy while logistics and sequencing were vital for their erection. But the
  • Innovative, flexible bridge formwork systems
    February 14, 2012
    Innovative formwork systems have been used to construct a variety of bridge structures. Patrick Smith reports. As part of the work on Germany's new A4 autobahn near Eisenach, the contracting joint venture awarded the formwork contract for two of the three viaducts to Doka. What makes this assignment so special to the company is that although the two steel composite bridges each have very different cross-sections, the JV is using the same overslung composite forming carriage to pour the carriageway slabs of
  • Almost gone: Canada’s old Port Mann Bridge deconstructed
    August 14, 2015
    Three years ago a welder’s cut halved Canada’s old Port Mann Bridge. David Arminas reports from the banks of the Fraser River. By the time this issue of World Highways reaches you, one of Canada’s iconic steel arch bridges will be a shadow of its former self. It’s been a three-year demolition job since the first cut across the deck of the old Port Mann Bridge just outside the city of Vancouver on Canada’s Pacific coast. A new 10-lane 2.2km Port Mann Bridge opened in 2012 (see box). It runs parallel to the o
  • The Lessons of the Genoa bridge collapse
    April 23, 2019
    The partial collapse of the Polcevera viaduct, better known as the Morandi Bridge, has prompted debate regarding the technical and administrative aspects of maintaining road infrastructures. We discussed it with the engineer Gabriele Camomilla, former Director of Research and Maintenance of the Società Autostrade, who coordinated the only major structural intervention performed on the bridge, carried out in the early 1990s