Polish road authority GDDKiA has approved the calling of 50 tenders for road construction projects worth a combined US$9.85 billion (PLN 32bn). GDDKiA has decided to allow contractors to carry out changes in one half of the projects supplied by the authority, which will, it says, allow the relations between the investor and the contractor to become more efficient. However, it can also act as an encouragement of the building companies to save on quality. Work on the road construction projects being put up fo
May 17, 2013 Read time: 2 mins
The Polish road authority 1361 GDDKiA has approved the calling of 50 tenders for road construction projects worth a combined €7.65 billion (PLN 32bn). GDDKiA has decided to allow contractors to carry out changes in one half of the projects supplied by the authority, which will, it says, allow the relations between the investor and the contractor to become more efficient. However, it can also act as an encouragement of the building companies to save on quality. Work on the road construction projects being put up for tender is due to begin next year.

However all is not rosy within Poland’s road construction sector as a long running dispute appears to have re-emerged. Austrian contractor 1332 Alpine Bau has halted construction of a bridge that forms part of A1 highway between Sosnica and Gorzyczki. The dispute centres on a guarantee payment requested by GDDKiA but which the contractor claims has a major impact on its finances for the work. The disagreement over the payment has also opened a long running dispute that centres on the design of the bridge dating back to 2009. Alpine Bau previously refused to construct the bridge to the design set out by GDDKiA. According to the contractor, this design could be unsafe without further modifications. This earlier dispute saw Alpine Bau’s contract for the section of the highway taken away by GDDKiA over claims that deadlines had not been met, as well as the deadlock over the bridge design. Following the loss of the contract, GDDKiA and Alpine Bau started a complex legal battle. Once this had been settled between the two parties, the construction firm was able to restart work. Now it appears that the dispute over the bridge design, a focal point of the earlier disagreement, has not been fully settled.

For more information on companies in this article

Related Content

  • Upgrade and new road projects in Poland to cost €4.33 billion in 2013
    March 19, 2013
    Polish spending on modernisation and new road projects will reach around €4.33 billion (PLN 18bn) in 2013. Among the planned investments are a section of the five express roads between Rawicz and Leszno, a section of the A1 motorway between Swierklam and Mszana, and a section of the A4 motorway between Korczowa and Jaroslaw. Private companies have been contracted to maintain around 1,000km of motorways and roads, which will result in savings achieved by the General Directorate of National Roads and Motorway
  • A1 Poland contract worth over €238.4mn signed by GDDKiA and consortium
    April 10, 2013
    Polish road authority GDDKiA has signed a contract with a consortium of Salini Polska, Przedsibiorstwo Budowy Drógi Mostów Kobylarnia and Impreglio for completing two sections of the A1 motorway. The combined value of two sections (Brzezie- Kowal and Czerniewice-Brzezie) stands at over €238.24 million (PLN 1bn). The works are due to start in the second quarter of 2013, with the completion expected to take 11 months on the Czerniewice-Brzezie section, and a year on the Kowal-Brzezie stretch.
  • STRABAG will lead A4 highway deal in Poland
    May 9, 2013
    Austrian contractor STRABAG is heading a consortium handling work to complete a section of Poland’s A4 highway between Krzyż and Dębica Pustynia. STRABAG’s subsidiary Heilit+Woerner is responsible for the contract, which was awarded by Poland’s General Directorate for National Roads and Highways (GDDKiA). The contract is worth €236 million (PLN 981 million), of which Heilit+Woerner has a 50% share. The work will be carried out over a 35km section of the route over and 18 month period. The work includes the
  • Poland: GDDKiA calls two S3 dual carriageway construction tenders
    June 13, 2017
    Poland’s road authority GDDKiA is going out to tender for construction of a 16km section of the S3 dual carriageway stretching between Bolkow and Kamienna Gora.