Funding problems for major Polish highway project

The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case. The Chinese contractor China Overseas Engineering Group Co (Covec) is appealing against a decision made by the Polish national road authority GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.
May 9, 2012 Read time: 3 mins
The long tale of woe concerning Poland’s troubled A2 highway project looks set to continue with the latest developments in the case.

The Chinese contractor China Overseas Engineering Group Co (2487 COVEC) is appealing against a decision made by the Polish national road authority 1361 GDDKiA. The Polish authorities cancelled the contract that COVEC had previously been awarded to build a section of the A2 highway between Warsaw and Lodz.

The highway is an important one as it will link the Polish and German capitals Warsaw and Berlin respectively. Covec’s deal was a landmark decision, the first time a Chinese firm had won a major construction contract in Europe. The firm won the tender process for the 50km highway stretch with a low bid that caused some controversy as other bidders complained about being undercut. The problems started soon after Covec commenced work, with materials prices spiralling and causing major problems for the Chinese firms. As delays with the work mounted and complaints from local sub-contractors over non-payment by the main contractor grew, Covec was forced to withdraw from the project in May. Covec has now complained that it has been unfairly treated by the Polish authorities and at present, the case looks likely to end up in the Polish courts.

Work on two sections of Poland’s A2 highway will now be constructed by two consortia. The 3281 Eurovia-3544 Warbud consortium will build the 29km A section, which will cost €246.63 million. The 20km C section will be built by the Boegl & Krysl-DSS consortium and will cost €188.54 million. The contracts were awarded by the GDDKiA.

Poland’s Ministry of Infrastructure is in talks with the 1166 European Bank for Reconstruction and Development (EBRD) and the 1054 European Investment Bank (EIB) as well as other financial institutions. The aim of the talks is to find solutions to highway financing issues, without increasing public debt. Before the end of 2011, two major highway tenders will be announced in Poland. One of these will be for work to the A2 highway between capital Warsaw and Poland's eastern border. The other will be for a 140km section of the A1 highway between Tuszyn and Pyrzowice. Experts say that the A1 project could be carried out under a public-private partnership (PPP) because the highway will carry heavy traffic volumes. A number of private partners have put themselves forward for this PPP proposal including 2296 Skanska and 7167 Meridiam.

Related Content

  • Canada: work officially starts on Montreal’s Champlain Bridge
    June 25, 2015
    Canada’s infrastructure minister, Denis Label, officially broke ground for Montreal’s replacement Champlain Bridge, saying the project will likely cost US$3.42 billion. The 3.4km Champlain Bridge Corridor Project, including spans and highway expansions, is expected to be completed by 2019. SNC-Lavalin, the 50% stakeholder in the winning consortium Signature on the Saint-Lawrence, recently announced it had finalised the deal with new Champlain Bridge owner Infrastructure Canada. Signature on the Saint-
  • Ring road for Sarajevo nears completion
    December 17, 2012
    The Sarajevo Ring Road in Bosnia and Herzegovina is expected to be completed by October 2012. The construction of the 5.6km long highway from Josanica to Butila is being carried out by a consortium of companies made up of HP Investing and Strabag. The completed Ring Road will be part of the future Corridor Vc motorway. Bosnia and Herzegovina Federal Minister of Transport and Telecoms, Enver Bijedic, and State Minister of Telecoms and Transport and Director of the roads company JP Ceste FBiH, Filip Vujevo, r
  • A1 Poland contract worth over €238.4mn signed by GDDKiA and consortium
    April 10, 2013
    Polish road authority GDDKiA has signed a contract with a consortium of Salini Polska, Przedsibiorstwo Budowy Drógi Mostów Kobylarnia and Impreglio for completing two sections of the A1 motorway. The combined value of two sections (Brzezie- Kowal and Czerniewice-Brzezie) stands at over €238.24 million (PLN 1bn). The works are due to start in the second quarter of 2013, with the completion expected to take 11 months on the Czerniewice-Brzezie section, and a year on the Kowal-Brzezie stretch.
  • Croatia rejects complaints over Peljeski Bridge tender
    April 6, 2018
    Croatia’s public procurement body has rejected complaints by all three international consortia over a winning low tender for the Peljeski bridge. Bids for construction of the four-lane 2.4km bridge were submitted in the middle of last year. The bridge will connect Croatian territory by traversing the Adriatic Sea’s Mali Ston Bay. Vehicles must currently head from Croatia into Bosnia to re-enter a peninsula that is Croatian territory. Croatia’s State Commission for Control of Public Ordering Processes