Skip to main content

Finley’s triple bridge design-build success in Israel

Finley Engineering Group (Finley) is providing segmental bridge design and construction engineering services on three design-build projects in Israel. Road 722 is a US$68.9 million project in Haifa awarded to Danya-Cebus. The project’s twin precast segmental bridges have a total length of 314m and six spans. The Road 722 Bridge is said to be based on the same cross section and erection method that Finley developed for Danya-Cebus and used on the Road 431 project (5 bridges), the Section 18 Interchange (6 br
April 9, 2013 Read time: 2 mins
5979 Finley Engineering Group (Finley) is providing segmental bridge design and construction engineering services on three design-build projects in Israel.

Road 722 is a US$68.9 million project in Haifa awarded to Danya-Cebus. The project’s twin precast segmental bridges have a total length of 314m and six spans. The Road 722 Bridge is said to be based on the same cross section and erection method that Finley developed for Danya-Cebus and used on the Road 431 project (5 bridges), the Section 18 Interchange (6 bridges); and the Benyamina Bridge (2 bridges) segmental bridge construction projects in Israel totalling $471 million.

Road 65/85 Nahal Amud & Nahal Acbara Bridges in Galilee is a $250 million project awarded to Shikun & Binui - 1572 Solel Boneh Building & Infrastructure to build the Upper Galilee interchange near Kibbutz Kadarim at the intersection of Road 65, running north from the Golani Junction and Road 85, and eastward from Carmiel.

The project’s bridges are precast concrete segmental bridges with three spans that will be 25m above the valley floor. The bridge design is said to be sensitive to the specific landscaping and historic value of the area. Nahal Amud bridges are twin six span bridges with a total length of 338m. Nahal Acbara bridges are twin three span bridges with a total length of 120m. Both bridges are said by Finley to be designed to accommodate future widening of the bridge.

Finally, the $170 million Road 1 Motzha Bridge near Jerusalem and Tel Aviv was awarded to Cebus-Rimon Industrialised Construction. Because this route is part of the major highway system and the main road into Jerusalem, it is one of the most important infrastructure projects that will be carried out by the Ministry of Transport and Roads Company in the coming years.

The challenging project is adjacent to religious archeological sites between two tunnels and the segmental bridge design is said by Finley to provide a method for building a structure with no impact to the culturally significant area. The completed project will see the creation of two 800m precast segmental bridges with three lanes in each direction.

For more information on companies in this article

Related Content

  • An Israeli contractor will build a key connection at Galilee
    May 22, 2012
    In Israel the contractor Shikun u'Binui Holdings has been awarded a road project worth some US$65.2 million. The tender was awarded by Israel National Roads Company and is for a four-year project. Under the terms of the deal Shikun u'Binui Solel Boneh Building and Infrastructure will upgrade the Upper Galilee interchange that connects Road 65 and Road 85. The project also includes widening both highways from two-lane to four-lane roads as well as building a small interchange near the Kahal village and const
  • Israel's new tunnel project
    April 20, 2012
    The Israel National Roads Company is opening the tender process for the project to drive new tunnels on Road no 1.
  • Jerusalem bottleneck route to be upgraded
    March 1, 2012
    The upgrading of Highway 1 between Sha'ar Hagay and the entrance to Jerusalem, Israel, a 2.5 billion NIS project (US$733 million), is expected to take five years to complete.
  • Israel interchange
    May 2, 2012
    A new US$350 million road project by the Israel National Roads Company will boost connectivity from the north to the centre of the country. The project is seeing the opening of new interchanges and roads in western Galilee. The aim of the project was to double the traffic capacity on Road 77, the Hamovil and Somech junctions and road No 79 that connects them.